ICC GENERAL REQUIREMENTS EXAM (2 LATEST
VERSIONS)
COMPLETE QUESTIONS AND DETAILED SOLUTIONS LATEST
UPDATE THIS YEAR JUST RELEASED
Question 1: A _________ is a classification assigned to a structure
based on risk category and the severity of the design earthquake
ground motion at the site.
Answer:
d.) Seismic force-resisting systems
Question 2: A special inspector is responsible for all of the
following except...
Answer:
a.) submitting RFI's
Question 3: placement of 3000 psi concrete for graded beams and
sampling to fabricate strength specimens requires what type of
special inspection?
Answer:
b.)continuous
Question 4: who is responsible for preparing the statement of
special inspection?
Answer:
a.)registered design professional
,Question 5: all of the following should be on a daily report except...
Answer:
b.)man count for the rebar contractor
Question 6: the special inspector shall furnish daily inspections to
the ________ and _________.
Answer:
a.) building official and registered design professional
Question 7: a special inspector is responsible for all of the
following except...
Answer:
c.) structural observation
Question 8: which of the following would typically not be needed by
the special inspector?
Answer:
d.) design calculations
Question 9: which of the following would typically be required for
work performed on the premises of an approved fabricator
Answer:
a.)no inspection
,Question 10: when discrepancies go uncorrected and a correction
notice is issued, who must be notified?
Answer:
b.)city inspector and registered design professional
Question 11: rebar placement for wall panels in a two story tilt up,
in seismic design category D, requires what type of special
inspection?
Answer:
a.) periodic
Question 12: continuous special inspection is required for all of the
following except...
Answer:
c.)post-installed mechanical anchors installed to anchor the bottoms of storage racks
to a 3000 psi concrete slab
Question 13: Structural observation
Answer:
b.) shall be provided for structures in seismic design category D,E, or F
Question 14: whenever strength tests are cast, what other tests
should be performed?
Answer:
b.) temperature, slump, and air content
, Question 15: prior to visiting a job site, the special inspector
should...
Answer:
d.)all of the above
Question 16: who shall prepare the statement of special
inspection?
Answer:
c.) Registered design professional
Question 17: an evaluation report...
Answer:
b.) presents the findings of a technical evaluation of a building product, certifying the
products compliance with the code requirements
Question 18: who can issue a stop work order?
Answer:
c.) Building official
Question 19: work that usually requires special inspection in the
field but is instead performed off-site on the premises of a
fabricator during fabrication...
Answer:
c.) does not require special inspection if the fabricator is registered and approved
VERSIONS)
COMPLETE QUESTIONS AND DETAILED SOLUTIONS LATEST
UPDATE THIS YEAR JUST RELEASED
Question 1: A _________ is a classification assigned to a structure
based on risk category and the severity of the design earthquake
ground motion at the site.
Answer:
d.) Seismic force-resisting systems
Question 2: A special inspector is responsible for all of the
following except...
Answer:
a.) submitting RFI's
Question 3: placement of 3000 psi concrete for graded beams and
sampling to fabricate strength specimens requires what type of
special inspection?
Answer:
b.)continuous
Question 4: who is responsible for preparing the statement of
special inspection?
Answer:
a.)registered design professional
,Question 5: all of the following should be on a daily report except...
Answer:
b.)man count for the rebar contractor
Question 6: the special inspector shall furnish daily inspections to
the ________ and _________.
Answer:
a.) building official and registered design professional
Question 7: a special inspector is responsible for all of the
following except...
Answer:
c.) structural observation
Question 8: which of the following would typically not be needed by
the special inspector?
Answer:
d.) design calculations
Question 9: which of the following would typically be required for
work performed on the premises of an approved fabricator
Answer:
a.)no inspection
,Question 10: when discrepancies go uncorrected and a correction
notice is issued, who must be notified?
Answer:
b.)city inspector and registered design professional
Question 11: rebar placement for wall panels in a two story tilt up,
in seismic design category D, requires what type of special
inspection?
Answer:
a.) periodic
Question 12: continuous special inspection is required for all of the
following except...
Answer:
c.)post-installed mechanical anchors installed to anchor the bottoms of storage racks
to a 3000 psi concrete slab
Question 13: Structural observation
Answer:
b.) shall be provided for structures in seismic design category D,E, or F
Question 14: whenever strength tests are cast, what other tests
should be performed?
Answer:
b.) temperature, slump, and air content
, Question 15: prior to visiting a job site, the special inspector
should...
Answer:
d.)all of the above
Question 16: who shall prepare the statement of special
inspection?
Answer:
c.) Registered design professional
Question 17: an evaluation report...
Answer:
b.) presents the findings of a technical evaluation of a building product, certifying the
products compliance with the code requirements
Question 18: who can issue a stop work order?
Answer:
c.) Building official
Question 19: work that usually requires special inspection in the
field but is instead performed off-site on the premises of a
fabricator during fabrication...
Answer:
c.) does not require special inspection if the fabricator is registered and approved