Q1: Project Management Fundamentals – Program
What is a program?
A. A group of related projects managed in a coordinated way
B. A single large project
C. A portfolio of unrelated projects
D. An ongoing operational function
Correct Answer: A
Rationale: A program is a group of related projects managed in a coordinated manner to obtain
benefits not available from managing them individually. [100% CORRECT]
Q2: Project Management Fundamentals – Portfolio
What is a portfolio?
A. A collection of projects, programs, and operations managed as a group to achieve strategic
objectives
B. A single project
C. A program
D. A phase
Correct Answer: A
Rationale: A portfolio is a collection of projects, programs, subsidiary portfolios, and operations
managed as a group to achieve strategic objectives. [100% CORRECT]
Q3: Project Management Fundamentals – Business Case
What is a business case?
A. A documented economic feasibility study used to establish the validity of the benefits of a project
B. A project charter
C. A project management plan
D. A project schedule
Correct Answer: A
Rationale: A business case is a documented economic feasibility study used to establish the validity
of the benefits of a selected component lacking sufficient definition. [100% CORRECT]
,2
Q4: Project Management Fundamentals – Benefits Realization
What is benefits realization?
A. The process of ensuring that project benefits are realized as planned
B. The process of closing the project
C. The process of planning the project
D. The process of executing the project
Correct Answer: A
Rationale: Benefits realization ensures that the benefits defined in the business case are achieved
and sustained after project completion. [100% CORRECT]
Q5: Project Management Fundamentals – Rolling Wave Planning
What is rolling wave planning?
A. An iterative planning technique where work is planned in detail for the near term and at a higher
level for the future
B. A technique for crashing the schedule
C. A technique for fast tracking
D. A technique for resource leveling
Correct Answer: A
Rationale: Rolling wave planning plans near-term work in detail while future work is planned at a
higher level, to be elaborated later. [100% CORRECT]
Q6: Project Management Fundamentals – Project Governance
What is project governance?
A. The framework for decision-making, roles, and responsibilities for the project
B. The project schedule
C. The project budget
D. The project charter
Correct Answer: A
Rationale: Project governance provides the framework for decision-making, defines roles and
responsibilities, and ensures alignment with organizational strategy. [100% CORRECT]
Q7: Project Management Fundamentals – Stakeholder Engagement
What is the goal of stakeholder engagement?
A. To work collaboratively with stakeholders to meet their needs and expectations
B. To ignore stakeholders
C. To manage only the project team
D. To avoid communication
Correct Answer: A
Rationale: Stakeholder engagement works collaboratively with stakeholders to meet their needs and
expectations, and to address issues as they arise. [100% CORRECT]
, 3
Q8: Project Management Fundamentals – Project Success Criteria
Which of the following is a common project success criterion?
A. Meeting scope, time, cost, and quality objectives
B. Completing the project regardless of quality
C. Ignoring stakeholder satisfaction
D. Avoiding change at all costs
Correct Answer: A
Rationale: Project success is typically measured by meeting scope, time, cost, and quality objectives
while satisfying stakeholder expectations. [100% CORRECT]
Q9: Project Management Fundamentals – Project Manager Skills
Which skill is most important for a project manager?
A. Communication
B. Technical coding
C. Accounting
D. Marketing
Correct Answer: A
Rationale: Communication is consistently ranked as the most important skill for project managers,
as they spend most of their time communicating. [100% CORRECT]
Q10: Project Management Fundamentals – Project Constraints
Which constraint is often called the “iron triangle”?
A. Scope, time, and cost
B. Quality, risk, and resources
C. Stakeholders, communication, and procurement
D. Planning, executing, and closing
Correct Answer: A
Rationale: The iron triangle (triple constraint) consists of scope, time, and cost. Quality is often
considered a fourth constraint. [100% CORRECT]
SECTION 2: ORGANIZATIONAL STRUCTURES AND PROJECT ENVIRONMENT – Questions 11–18
Q11: Organizational Structures – Functional
In a functional organization, who typically controls the project budget?
A. Functional manager
B. Project manager
C. Project coordinator
D. Project expeditor
Correct Answer: A
Rationale: In a functional organization, the functional manager controls the budget and resources,