375 Milestone 4 Exam Test A+ Questions
and Answers Verified Solutions Latest
Update 2026/2027
Answer:
lower project costs and/or shortened project schedule.
■ An increase in one constraint.
Answer:
may have a negative impact on the other constraints
■ A shortened project schedule may lead to.
Answer:
increased labor costs to ensure that a project is completed on time.
■ Rolling Wave Planning.
Answer:
-A form of progressive elaboration planning where the work to be accomplished in the near term is
planned in detail and future work is planned at a higher level of the WBS.
-Can only see what is happening right now- no detail for future events
■ Templates.
Answer:
A standard activity list or a portion of an activity list form a previous project is often usable as a
________ for a new project. The related activity attributes information in the _________ can also
contain other descriptive information useful in defining activities.
- Can also be used to identify typical schedule milestones.
■ Activity List
Answer:
, A comprehensive list including all schedule activities required on the project.
-Includes the activity identifier and a scope of work description for each activity in sufficient detail
to ensure that project team members understand what work is required to be completed
■ Activity Attributes
Answer:
The description of the activity by identifying the multiple components associated with each
activity. The components for each activity evolve over time.
■ Milestone
Answer:
A significant point or event in a project
■ Milestone List
Answer:
identifies all milestones and indicates whether the millstone is mandatory, such as those required by
contract, or optional, such as those based upon historical information
■ Sequence Activities
Answer:
The logical relationship where completion of the successor schedule activity is dependent upon the
initiation of the predecessor schedule activity
■ Gantt Chart
Answer:
Graphic display of schedule related information. In the typical bar-chart, schedule activities or
WBS components are listed down the left side of the chart, dates are shown across the top, and
activity durations are shown as date-place horizontal bars
■ Precedence Diagramming Method
Answer:
A schedule network diagramming technique in which schedule activities are represented by boxes
(or nodes).
-Schedule activities are graphically linked by one or more logical relationships to show the
sequence in which the activities are to be performed
and Answers Verified Solutions Latest
Update 2026/2027
Answer:
lower project costs and/or shortened project schedule.
■ An increase in one constraint.
Answer:
may have a negative impact on the other constraints
■ A shortened project schedule may lead to.
Answer:
increased labor costs to ensure that a project is completed on time.
■ Rolling Wave Planning.
Answer:
-A form of progressive elaboration planning where the work to be accomplished in the near term is
planned in detail and future work is planned at a higher level of the WBS.
-Can only see what is happening right now- no detail for future events
■ Templates.
Answer:
A standard activity list or a portion of an activity list form a previous project is often usable as a
________ for a new project. The related activity attributes information in the _________ can also
contain other descriptive information useful in defining activities.
- Can also be used to identify typical schedule milestones.
■ Activity List
Answer:
, A comprehensive list including all schedule activities required on the project.
-Includes the activity identifier and a scope of work description for each activity in sufficient detail
to ensure that project team members understand what work is required to be completed
■ Activity Attributes
Answer:
The description of the activity by identifying the multiple components associated with each
activity. The components for each activity evolve over time.
■ Milestone
Answer:
A significant point or event in a project
■ Milestone List
Answer:
identifies all milestones and indicates whether the millstone is mandatory, such as those required by
contract, or optional, such as those based upon historical information
■ Sequence Activities
Answer:
The logical relationship where completion of the successor schedule activity is dependent upon the
initiation of the predecessor schedule activity
■ Gantt Chart
Answer:
Graphic display of schedule related information. In the typical bar-chart, schedule activities or
WBS components are listed down the left side of the chart, dates are shown across the top, and
activity durations are shown as date-place horizontal bars
■ Precedence Diagramming Method
Answer:
A schedule network diagramming technique in which schedule activities are represented by boxes
(or nodes).
-Schedule activities are graphically linked by one or more logical relationships to show the
sequence in which the activities are to be performed