CQM-C Exam Questions and Answers
2025/2026 – Construction Quality
Management for Contractors Study Guide
Prepare for the CQM-C certification exam with 100 practice
questions covering quality control plans, contractor
responsibilities, submittals, and the three phases of control. This
study guide aligns with USACE and NAVFAC requirements for
Construction Quality Management for Contractors. Includes
detailed answers and explanations for each question. Updated
for 2025/2026. Ideal for QC Managers seeking certification or
recertification.
Section 2: Exam Questions and Answers
Four answer choices per question (A–D). Correct answer highlighted.
1. The purpose of Construction Quality Management is to:
(a) Minimize project costs
(b) Achieve quality established by requirements
(c) Speed up construction timelines
(d) Reduce contractor oversight
ANS: Achieve quality established by requirements
Explanation: Focuses on meeting planned quality standards.
2. Construction Quality Management ensures construction is performed:
(a) With minimal supervision
(b) According to plans and specifications
(c) Using the cheapest materials
(d) Without safety protocols
ANS: According to plans and specifications
Explanation: Adheres to contract requirements.
3. Partnering relationships are based upon:
(a) Competitive bidding
(b) Building trust and common goals
(c) Reducing government involvement
,2|Page
(d) Maximizing individual profits
ANS: Building trust and common goals
Explanation: Emphasizes collaboration.
4. It is the responsibility of Quality Assurance Personnel to:
(a) Perform all construction tasks
(b) Periodically verify the contractor’s control system
(c) Design the project plans
(d) Handle financial payments
ANS: Periodically verify the contractor’s control system
Explanation: Ensures effective quality control.
5. An effective contractor quality control program will:
(a) Delay project completion
(b) Incentivize correct work the first time
(c) Increase overhead costs
(d) Eliminate safety measures
ANS: Incentivize correct work the first time
Explanation: Promotes efficiency and profit.
6. The success or failure of contractors is based upon:
(a) Government funding levels
(b) Ability to control costs and maintain quality
(c) Number of employees
(d) Project location
ANS: Ability to control costs and maintain quality
Explanation: Key to operational success.
7. Quality Assurance Personnel have the responsibility to:
(a) Build the project structures
(b) Require contractors to maintain specified quality
(c) Approve all submittals
(d) Manage the construction schedule
ANS: Require contractors to maintain specified quality
Explanation: Ensures contract compliance.
8. Inspection is:
(a) The design of construction plans
(b) The process of examining ongoing and completed work
(c) The approval of budgets
(d) The training of workers
ANS: The process of examining ongoing and completed work
Explanation: Verifies compliance with requirements.
, 3|Page
9. The Quality Control (QC) organization must be:
(a) Independent of the production organization
(b) Part of the marketing department
(c) Supervised by the government
(d) Subcontracted to a third party
ANS: Independent of the production organization
Explanation: Prevents conflicts of interest regarding quality.
10. Who is responsible for developing the Contractor Quality Control (CQC)
Plan?
(a) The Contracting Officer
(b) The Quality Assurance Representative
(c) The Contractor
(d) The Architect/Engineer
ANS: The Contractor
Explanation: The contractor is responsible for the means and methods of quality
control.
11. The three phases of control are Preparatory, Initial, and:
(a) Final
(b) Follow-up
(c) Intermediate
(d) Definitive
ANS: Follow-up
Explanation: The three phases are Preparatory, Initial, and Follow-up.
12. The Preparatory Phase is performed:
(a) During the actual construction
(b) Before beginning work on a definable feature of work
(c) After the work is complete
(d) Only when problems arise
ANS: Before beginning work on a definable feature of work
Explanation: Ensures everything is ready before starting.
13. The Initial Phase is performed:
(a) As soon as the first portion of the work is started
(b) Before mobilizing equipment
(c) At the end of the project
(d) During the final inspection
ANS: As soon as the first portion of the work is started
Explanation: Establishes the standard for the rest of the work.
14. The Follow-up Phase consists of:
(a) Continuous checks to ensure control