IPMA Exam Questions with Verified Correct Answers

Document preview thumbnail
Voorbeeld 4 van de 61 pagina's

IPMA Exam Questions with Verified Correct Answers

Voorbeeld van de inhoud

IPMA Exam Questions with Verified Correct
Answers
Which option is the most important factor to consider in deciding whether to use a

fixed-price (lump-sum) contract or a cost-reimbersable one?

A) How well defined the scope is

B) The expected duration of the project

C) The expected value of the contract

D) Relevant environmental regulations

A) How well defined the scope is

Cost & schedule risk can be directly mitigated through the use of:

A. Simulations

B. Reserves

C. Decision Trees

D. Status Reports

B. Reserves

Which type of behavior from the project manager is most likely to help produce a

successful project?

A. Uses business stories to reinforce important points

B. Creates stress in order to ensure high productivity

C. Minimizes the importance of cultural differences

,D. Uses humor to deflect criticism

A. Uses business stories to reinforce important points

When the scope is poorly defined or poorly understood, there is a greater-than-

normal need for:

A. A large project team

B. Cooperation and communication among the stakeholders

C. Daily reporting of actual expenditures

D. The use of automated scheduling tools

B. Cooperation and communication among the stakeholders

A project charter



A. Expresses management's commitment to the project

B. Is normally issued by the project manager

C. Is used mostly when dealing with potential sellers of long-lead-time items

D. Is one of the key outputs of project planning

A. Expresses management's commitment to the project

Project management is:



A. A large number of related activities grouped into stages

B. Scheduling activities that support business objectives

C. A system of interconnected processes that occur once in each project

D. An effective approach to developing new products and services

,D. An effective approach to developing new products and services

The project's communication requirements are most likely to be affected by:

A. Which word processing software is used

B. The installation of engineering workstations

C. The biases of the stakeholders

D. the use of computer-aided design tools

C. The biases of the stakeholders

Which document would have the most detailed description of the work of the project?

A. Work breakdown structure

B. Milestone chart

C. Scope management plan

D. Risk response list

A. Work breakdown structure

Resource leveling will often:



A. Have little to no effect of individual activity durations

B. Have little to no effect on the overall project duration

C. Increase the most likely duration of the project

D. Increase the most likely project cost

C. Increase the most likely duration of the project

, Which type of behavior from the project manager is most likely to help produce a

successful project?

A. Communicates on the basis of “need to know.”

B. Is pessimistic to keep expectations low

C. Consistently supports the majority view

D. Listens carefully to others

D. Listens carefully to others

Primary responsibility for quality in a project rests with the:

A. Project Manager

B. Project Engineer

C. Quality Department Manager

D. Sponsor

A. Project Manager

Which item is least likely to require interpretation by a qualified legal expert?

A. Copyrights

B. Contracts

C. Technical Standards

D. Government Regulations

C. Technical Standards

Which option is most likely to be included in a project closeout report?

Documentinformatie

Geüpload op
9 september 2026
Aantal pagina's
61
Geschreven in
2026/2027
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$15.99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kan je een ander document kiezen. Je kan het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
KenAli
2.6
(18)
Verkocht
114
Volgers
5
Items
24575
Laatst verkocht
1 week geleden



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen