ARKANSAS CONSTRUCTION MANAGER
CERTIFICATION EXAM QUESTIONS WITH
CORRECT ANSWERS AND RATIONALES LATEST
2026-2027 UPDATE| EXCELLENCY GUARANTEE
1. What is the primary responsibility of a construction manager?
A. Performing all construction work personally
B. Coordinating the resources, schedule, cost, quality, and safety of a
construction project
C. Designing every structural component
D. Approving building permits on behalf of the state
Correct Answer: B
Rationale: A construction manager coordinates project resources and
activities to achieve the required scope, schedule, cost, quality, and
safety objectives. The manager does not necessarily perform the
physical construction or design every component.
2. Under Arkansas contractor licensing rules, construction
management may be performed by a licensed contractor when:
A. The contractor has no active license
B. It is within the scope of the contractor's license
C. The project is privately funded
D. The project has fewer than 10 workers
Correct Answer: B
Rationale: Arkansas rules provide that a licensed contractor may
perform construction management within the scope of the license held.
,3. Which organization administers contractor licensing in
Arkansas?
A. Arkansas Department of Transportation
B. Arkansas Contractors Licensing Board
C. Arkansas State Police
D. Arkansas Department of Education
Correct Answer: B
Rationale: The Arkansas Contractors Licensing Board administers
contractor licensing under Arkansas contractor licensing law.
4. What is a major purpose of construction scheduling?
A. Eliminate the need for contracts
B. Establish the sequence and timing of project activities
C. Determine employee tax rates
D. Replace construction drawings
Correct Answer: B
Rationale: Scheduling establishes when activities should occur and how
they relate to one another, helping control project duration and
resources.
5. Which scheduling method identifies activities and their logical
relationships?
A. Critical Path Method
B. Balance sheet method
, C. Straight-line depreciation
D. Unit-price method
Correct Answer: A
Rationale: Critical Path Method (CPM) uses activities, durations,
dependencies, and network relationships to determine the project
schedule and critical path.
6. What is the critical path?
A. The least expensive sequence of activities
B. The sequence of activities that determines the minimum project
duration
C. The path used by emergency vehicles
D. The contractor's preferred delivery route
Correct Answer: B
Rationale: The critical path is the longest-duration sequence of
dependent activities and determines the shortest possible project
completion time under the modeled conditions.
7. An activity with zero total float is generally:
A. Nonessential
B. On the critical path
C. Already completed
D. Outside the contract
Correct Answer: B
Rationale: Activities with zero total float are normally critical because
delaying them can delay project completion.
CERTIFICATION EXAM QUESTIONS WITH
CORRECT ANSWERS AND RATIONALES LATEST
2026-2027 UPDATE| EXCELLENCY GUARANTEE
1. What is the primary responsibility of a construction manager?
A. Performing all construction work personally
B. Coordinating the resources, schedule, cost, quality, and safety of a
construction project
C. Designing every structural component
D. Approving building permits on behalf of the state
Correct Answer: B
Rationale: A construction manager coordinates project resources and
activities to achieve the required scope, schedule, cost, quality, and
safety objectives. The manager does not necessarily perform the
physical construction or design every component.
2. Under Arkansas contractor licensing rules, construction
management may be performed by a licensed contractor when:
A. The contractor has no active license
B. It is within the scope of the contractor's license
C. The project is privately funded
D. The project has fewer than 10 workers
Correct Answer: B
Rationale: Arkansas rules provide that a licensed contractor may
perform construction management within the scope of the license held.
,3. Which organization administers contractor licensing in
Arkansas?
A. Arkansas Department of Transportation
B. Arkansas Contractors Licensing Board
C. Arkansas State Police
D. Arkansas Department of Education
Correct Answer: B
Rationale: The Arkansas Contractors Licensing Board administers
contractor licensing under Arkansas contractor licensing law.
4. What is a major purpose of construction scheduling?
A. Eliminate the need for contracts
B. Establish the sequence and timing of project activities
C. Determine employee tax rates
D. Replace construction drawings
Correct Answer: B
Rationale: Scheduling establishes when activities should occur and how
they relate to one another, helping control project duration and
resources.
5. Which scheduling method identifies activities and their logical
relationships?
A. Critical Path Method
B. Balance sheet method
, C. Straight-line depreciation
D. Unit-price method
Correct Answer: A
Rationale: Critical Path Method (CPM) uses activities, durations,
dependencies, and network relationships to determine the project
schedule and critical path.
6. What is the critical path?
A. The least expensive sequence of activities
B. The sequence of activities that determines the minimum project
duration
C. The path used by emergency vehicles
D. The contractor's preferred delivery route
Correct Answer: B
Rationale: The critical path is the longest-duration sequence of
dependent activities and determines the shortest possible project
completion time under the modeled conditions.
7. An activity with zero total float is generally:
A. Nonessential
B. On the critical path
C. Already completed
D. Outside the contract
Correct Answer: B
Rationale: Activities with zero total float are normally critical because
delaying them can delay project completion.