A Florida residential contractor is preparing a written contract for a
$180,000 home renovation. The owner wants the contract to state only
the total price and the anticipated completion date, leaving the detailed
scope of work to be discussed verbally as construction progresses. What
is the greatest contract-administration risk created by this approach?
A. The contractor will automatically lose the right to collect any
payment
B. The absence of a sufficiently defined scope makes disputes
concerning included and excluded work much more likely
C. The owner becomes responsible for all subcontractor coordination
D. The contractor is prohibited from obtaining a building permit
Answer: B
Rationale: A clearly defined scope of work is fundamental to contract
administration because it establishes what the contractor has agreed to
furnish. Without sufficient detail concerning materials, labor,
allowances, exclusions, specifications, and responsibilities,
disagreements can arise over whether additional work is included in
the contract price. A vague scope does not automatically eliminate the
1
,contractor's right to payment, nor does it transfer ordinary project
responsibilities to the owner.
2.
A residential contractor receives architectural drawings that conflict with
the written project specifications. The drawings indicate one type of
exterior door while the specifications identify another. What should the
contractor generally do first?
A. Install whichever door is less expensive
B. Allow the superintendent to choose the door without documentation
C. Seek clarification from the appropriate design/contract authority
before proceeding with the affected work
D. Install both doors and submit the difference as a change order
Answer: C
Rationale: When contract documents conflict, proceeding without
clarification can create responsibility and payment disputes. The
contractor should identify the discrepancy, document it, and obtain an
authorized interpretation or clarification before performing the
affected work. The contractor should not unilaterally select the least
expensive option or manufacture a change order simply because the
documents conflict.
3.
A homeowner asks a residential contractor to add a screened porch after
the original contract has been signed. The work will increase the
contract price by $24,000. Which approach provides the strongest
contract-administration protection?
2
,A. Perform the work immediately based solely on the owner's verbal
request
B. Prepare a written change order describing the additional work and
price adjustment and obtain appropriate authorization
C. Tell the subcontractor to bill the owner directly
D. Add the cost to the final invoice without notifying the owner
Answer: B
Rationale: A written change order establishes what has changed, the
associated price adjustment, and, when applicable, the effect on the
schedule. This documentation helps establish mutual agreement and
prevents later disputes concerning authorization, scope, cost, and
completion time.
4.
A contractor discovers that site conditions differ materially from those
reasonably indicated in the contract documents. The unexpected
condition will substantially increase excavation costs. What is the most
appropriate contract-administration response?
A. Conceal the condition until the project is completed
B. Document the condition and notify the appropriate contracting party
before proceeding with materially affected work
C. Immediately terminate all subcontractors
D. Automatically double the entire contract price
Answer: B
Rationale: Unexpected site conditions should be documented promptly,
including photographs, measurements, location information, and
cost/schedule impacts. Contract provisions may establish specific
notice procedures. Early written notice allows the parties to evaluate
3
, entitlement and determine how the condition should be addressed
before additional costs accumulate.
5.
A residential contractor wants to hire a subcontractor for electrical work.
The subcontractor says, “I don't currently have the required license, but
my cousin's company has one and will let us use its license number.”
What should the contractor do?
A. Accept the arrangement if the price is reasonable
B. Accept it if the homeowner approves
C. Refuse the arrangement and verify that the properly authorized
contractor performs the regulated work
D. Use the cousin's license only on the permit application
Answer: C
Rationale: A contractor should not structure a project around the
unauthorized use or “borrowing” of another person's or business's
license. Florida's contracting statutes regulate who may engage in
contracting and establish restrictions on unlicensed contracting.
Contract administration must include verification of licensing
responsibilities rather than relying on informal arrangements.
6.
A residential contractor is awarded a project that requires a building
permit. The owner says, “Start demolition today and we'll take care of
the permit later.” What is the best response?
A. Start immediately because demolition never requires authorization
B. Begin only after determining and satisfying the applicable permit
requirements