Project Management Professional (PMP) - Exam Preparation comprehensive
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
Project Management Professional (PMP) EXAM
Project Management Professional (PMP) EXAM - (ANSWER)Project Management Professional (PMP)
EXAM
Project Management Professional (PMP) EXAM
You are developing the resource management plan for a project. Which is the best tool for linking work
packages from the projects work breakdown structure to the resources listed in the organizational
breakdown structure? - (ANSWER)The Responsibility Assignment Matrix (RAM)
A high level of responsibility assignment matrix may show key project phases or deliverables only and list
departments rather than individuals
You are currently defining the work that will be required to complete a product that will be produced by
a project that you are managing. Which item are you currently working on? - (ANSWER)Project Scope
Project scope describes the project deliverables and the work that must be performed to create this
product, service, or result for the stakeholders. This includes the work needed to fulfill any specified
features and functions outlines. Once the project scope is determined, the project statement can be
created
,Project Management Professional (PMP) - Exam Preparation comprehensive
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
When evaluating the completion of a project, against which document is project completion measured?
- (ANSWER)Project Management Plan
Used to measure the scope of a project to ensure project completion. Contains information from
previous project phases. Evaluating this information ensures that all of the project objectives have been
mat and that all project work is complete
Before you can begin checking the quality of the process, what other piece of information do you
require? - (ANSWER)The Data Standards for the Given Process
The data standards or quality metrics for a given process are one of the inputs needed when managing
quality. Quality metrics are specific measurement values
You are re-evaluating cost related risks. Which documentation would include project costs that have
been incurred? - (ANSWER)Work Performance Data
The costs incurred would be a part of the work performance data, which is an input of monitor risks.
Other information included with the work performance data includes the status on deliverables and
schedule progress
You are the project manager and you have noticed that project efficiency and effectiveness levels have
decreased. Which process is MOST closely associated with continuous process improvement? -
(ANSWER)Manage Quality
Manage quality is the means by which you audit the quality requirements established during the Plan
Quality Management process.
, Project Management Professional (PMP) - Exam Preparation comprehensive
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
After completing several tasks involved with the process of officially closing a project, all that remains is
to archive project information. Which of the following is information that is archived during this process.
- (ANSWER)Lessons Learned
This information is always archived at the end of a project. Some of the information would include
lessons learned, new techniques, what went wrong, and what went right
You have determined that some project objectives will exceed the risk thresholds set by the organization.
What should you do first? - (ANSWER)Advise the project sponsor of the situation
It is the project sponsors responsibility to decide on a course of action when the projects' objectives are
going to be exceeded
You are managing a landscaping project. You are currently in the Monitor Risks process to address a
problem that resulted with a flower provider. Besides monitoring and controlling risk, what is a
secondary purpose of this process? - (ANSWER)Ensure that project assumptions are still valid
You make sure risks are still relevant , you have to make sure risk management policies are being
followed and that the contingency plan is in line with the current assessments
You must provide management with a project schedule that displays the project as a summary of the
work packages only. The schedule also needs to display the progress of each work package. What is the
best way to display this information? - (ANSWER)Bar Chart
Used to present schedules. The length of each bar corresponds to the duration of the work package it
represents. They are generally easy to read and commonly used in management presentations
You are at a critical stage in your project. You have just been informed that the parts you require are no
longer available from the supplier with whom you have signed a contract to supply those parts. What
should you do first? - (ANSWER)Refer to the risk register to determine the appropriate risk response
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
Project Management Professional (PMP) EXAM
Project Management Professional (PMP) EXAM - (ANSWER)Project Management Professional (PMP)
EXAM
Project Management Professional (PMP) EXAM
You are developing the resource management plan for a project. Which is the best tool for linking work
packages from the projects work breakdown structure to the resources listed in the organizational
breakdown structure? - (ANSWER)The Responsibility Assignment Matrix (RAM)
A high level of responsibility assignment matrix may show key project phases or deliverables only and list
departments rather than individuals
You are currently defining the work that will be required to complete a product that will be produced by
a project that you are managing. Which item are you currently working on? - (ANSWER)Project Scope
Project scope describes the project deliverables and the work that must be performed to create this
product, service, or result for the stakeholders. This includes the work needed to fulfill any specified
features and functions outlines. Once the project scope is determined, the project statement can be
created
,Project Management Professional (PMP) - Exam Preparation comprehensive
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
When evaluating the completion of a project, against which document is project completion measured?
- (ANSWER)Project Management Plan
Used to measure the scope of a project to ensure project completion. Contains information from
previous project phases. Evaluating this information ensures that all of the project objectives have been
mat and that all project work is complete
Before you can begin checking the quality of the process, what other piece of information do you
require? - (ANSWER)The Data Standards for the Given Process
The data standards or quality metrics for a given process are one of the inputs needed when managing
quality. Quality metrics are specific measurement values
You are re-evaluating cost related risks. Which documentation would include project costs that have
been incurred? - (ANSWER)Work Performance Data
The costs incurred would be a part of the work performance data, which is an input of monitor risks.
Other information included with the work performance data includes the status on deliverables and
schedule progress
You are the project manager and you have noticed that project efficiency and effectiveness levels have
decreased. Which process is MOST closely associated with continuous process improvement? -
(ANSWER)Manage Quality
Manage quality is the means by which you audit the quality requirements established during the Plan
Quality Management process.
, Project Management Professional (PMP) - Exam Preparation comprehensive
Questions and Answers with 100% Correct Answers | Latest Version Already
Graded A+
After completing several tasks involved with the process of officially closing a project, all that remains is
to archive project information. Which of the following is information that is archived during this process.
- (ANSWER)Lessons Learned
This information is always archived at the end of a project. Some of the information would include
lessons learned, new techniques, what went wrong, and what went right
You have determined that some project objectives will exceed the risk thresholds set by the organization.
What should you do first? - (ANSWER)Advise the project sponsor of the situation
It is the project sponsors responsibility to decide on a course of action when the projects' objectives are
going to be exceeded
You are managing a landscaping project. You are currently in the Monitor Risks process to address a
problem that resulted with a flower provider. Besides monitoring and controlling risk, what is a
secondary purpose of this process? - (ANSWER)Ensure that project assumptions are still valid
You make sure risks are still relevant , you have to make sure risk management policies are being
followed and that the contingency plan is in line with the current assessments
You must provide management with a project schedule that displays the project as a summary of the
work packages only. The schedule also needs to display the progress of each work package. What is the
best way to display this information? - (ANSWER)Bar Chart
Used to present schedules. The length of each bar corresponds to the duration of the work package it
represents. They are generally easy to read and commonly used in management presentations
You are at a critical stage in your project. You have just been informed that the parts you require are no
longer available from the supplier with whom you have signed a contract to supply those parts. What
should you do first? - (ANSWER)Refer to the risk register to determine the appropriate risk response