◍ No work should be performed and no money should be paid until after the
____ day cancellation period?.
Answer: 3 days
◍ Types of Project Submittals.
Answer: Shop Drawings, Product data, and Samples
◍ How many days does a contractor or salesperson have to honor valid notice
of cancellation?.
Answer: 10 business days
◍ When a member is designed so that under the working load there are no
tensile stresses in it, then the concrete is said to be fully prestressed. On the
other hand, if tensile stresses are allowed to be produced in the member
under working load, then it is termed partially prestressed (the process of
applying a percentage of the final force at some earilier time than the normal
72 hours).
Answer: For partial prestressing additional mild steel rebar may be required
to control cracking under tension. For economic reasons, partial prestressing
is most common for of prestressing used in structures. Sufficient
prestressing steel is used to offset most of the member self-weight and other
sustained dead loads. Occasionally a small portion of live load is also
included. The tension produced by the remainder of live load is resisted by
the combination of stressed and non-stressed steel, resulting in economical
structures. THE BONDED STEEL REBAR assures control of the crack
, width and distribution, should secondary effects or overloading cause the
member to crack.
◍ Wire rope shall not be used if?.
Answer: In any length of eight diameters, the total number of visible broken
wires exceeds 10 percent of the total number of wires, or if rope shows other
signs of excessive wear, corrosion, or defect
◍ When would an architect or engineer involved with an
H. I. project need a contractor's license?.
Answer: If they are physically performing H.I. functions outside the scope
of an architect or engineer.
◍ What legal entity is a contractor required to be?.
Answer: A contractor may be an individual, a firm, a company, a
partnership, or a corporation.
◍ What is "home improvement" (
H. I.)? (C R R R R A A I).
Answer: the construction, repair, remodeling, alteration, rehabilitation,
renovation, improvement, or addition to any land or building used as a
residence or dwelling place.
◍ What type of guarantees or warranties can NOT be made?.
Answer: "lifetime" guarantees or warranties
◍ Valve protection caps shall not be used for lifting cylinders from one
vertical position to another..
Answer: Bars shall not be used under valves or valve protection caps to pry
cylinders loose when frozen. Warm, not boiling, water shall be used to thaw
cylinder loose
◍ Proctor Tests.
Answer: The standard Proctor test was developed in early 1930s by RR
Proctor, a field engineer for the City of Los Angeles. Applying heavy
weight to a completely dry soil sample won't acieve much increase in
density. When water is added it's much easier to increase the density. Water
, acts as a lubricant. The standard Proctor test is usually specified for fill
material designated for use under building slabs and sidewalks, and in utility
trenches under grassy areas. A sampl of the proposed fill material is crushed
so it can pass thru a 3/4inch sieve. A steel cylinder mold is filled with the
sample in 3 layers. Each layer is struck 25 times with a 5.5lb, 2inch diameter
hammer before the next layer is added.
◍ Legal Forms of Business Organizations.
Answer: 1. Sole Proprietorship: single-person ownership. Simplest form of
ownership2. Partnership: include at least to people to be legal. Partners are
fully responsible for all debts incurred by any one member. A limited
partner is only liable to the extent of his or her investment.3. Corporation:
most complex of the 3 types. Formal meetings must be held for any major
decision.
◍ Head lap, top lap and exposure.
Answer: The 2 inch lap where the shingles are three layers thick is the lead
lap. Top lap is where shingles are at least two layers thick. Head lap is
where shingles are three layers thick.Top Lap = W-E or E+HLHead Lap =
TL -E or W -2EExposure = (W-HL) / 2
◍ How long can a contractor elect to secure a bond or participate in DCA's
Home Improvement Trust Fund?.
Answer: Every 2 years
◍ May a
H. I. Contractor assign the task of getting permits, exemptions or C/O to the
home owner (customer)?.
Answer: No, The prime contractor must secure all necessary permits,
licenses, Certificates of Occupancy, or exemptions necessary to complete
the contract in accordance with state and local building laws.
◍ When ascending or descending a ladder.
Answer: The user shall face the ladder
◍ Fire-resistance rating.
, Answer: Shaft enclosures shall have a fire-resistance rating of not less than 2
hours where connecting four stories or more, not less than 1 hour where
connecting less than four stories.
◍ How many business locations can a
H. I. Contractor's license cover?.
Answer: One. A seperate license is required for each place of business.
◍ Must a subcontractor be seperately licensed by DCA?.
Answer: Yes, this includes electricians and plumbers.
◍ What system installations are part of
H. I.? (4).
Answer: Central heating/air conditioning, Central vacuum, Doors, windows,
awnings, and Communication systems.
◍ Scaffold casters and wheels shall be?.
Answer: Locked with positive wheel and/or wheel and swivel locks, or
equivalent means, to prevent movement of the scaffold while the scaffold is
used on stationary manner.
◍ Horizontal lifelines shall be designed, installed, and used, under the
supervision of a qualified person.
Answer: as part of a complete personal fall arrest system, which maintains a
safety factor of a least two
◍ Who must obtain building and improvement permits?.
Answer: The prime contractor.
◍ Where should quantities of flammable liquid in excess of 25 gallons be
stored in that is acceptable or approved?.
Answer: Acceptable wooden storage and Approved metal storage cabinets.
Cabinets shall be labeled in conspicuous lettering "Flammable-Keep Away
from Open Flames"
◍ Each scaffold unit shall be installed so that the space between adjacent units
and the space between the platform and the uprights is?.
CONTRACTOR SEMINAR FINAL TEST 2026
QUESTIONS WITH CORRECT ANSWERS
GRADED A+
◍ No work should be performed and no money should be paid until after the
____ day cancellation period?.
Answer: 3 days
◍ Types of Project Submittals.
Answer: Shop Drawings, Product data, and Samples
◍ How many days does a contractor or salesperson have to honor valid notice
of cancellation?.
Answer: 10 business days
◍ When a member is designed so that under the working load there are no
tensile stresses in it, then the concrete is said to be fully prestressed. On the
other hand, if tensile stresses are allowed to be produced in the member
under working load, then it is termed partially prestressed (the process of
applying a percentage of the final force at some earilier time than the normal
72 hours).
Answer: For partial prestressing additional mild steel rebar may be required
to control cracking under tension. For economic reasons, partial prestressing
is most common for of prestressing used in structures. Sufficient
prestressing steel is used to offset most of the member self-weight and other
sustained dead loads. Occasionally a small portion of live load is also
included. The tension produced by the remainder of live load is resisted by
the combination of stressed and non-stressed steel, resulting in economical
structures. THE BONDED STEEL REBAR assures control of the crack
, width and distribution, should secondary effects or overloading cause the
member to crack.
◍ Wire rope shall not be used if?.
Answer: In any length of eight diameters, the total number of visible broken
wires exceeds 10 percent of the total number of wires, or if rope shows other
signs of excessive wear, corrosion, or defect
◍ When would an architect or engineer involved with an
H. I. project need a contractor's license?.
Answer: If they are physically performing H.I. functions outside the scope
of an architect or engineer.
◍ What legal entity is a contractor required to be?.
Answer: A contractor may be an individual, a firm, a company, a
partnership, or a corporation.
◍ What is "home improvement" (
H. I.)? (C R R R R A A I).
Answer: the construction, repair, remodeling, alteration, rehabilitation,
renovation, improvement, or addition to any land or building used as a
residence or dwelling place.
◍ What type of guarantees or warranties can NOT be made?.
Answer: "lifetime" guarantees or warranties
◍ Valve protection caps shall not be used for lifting cylinders from one
vertical position to another..
Answer: Bars shall not be used under valves or valve protection caps to pry
cylinders loose when frozen. Warm, not boiling, water shall be used to thaw
cylinder loose
◍ Proctor Tests.
Answer: The standard Proctor test was developed in early 1930s by RR
Proctor, a field engineer for the City of Los Angeles. Applying heavy
weight to a completely dry soil sample won't acieve much increase in
density. When water is added it's much easier to increase the density. Water
, acts as a lubricant. The standard Proctor test is usually specified for fill
material designated for use under building slabs and sidewalks, and in utility
trenches under grassy areas. A sampl of the proposed fill material is crushed
so it can pass thru a 3/4inch sieve. A steel cylinder mold is filled with the
sample in 3 layers. Each layer is struck 25 times with a 5.5lb, 2inch diameter
hammer before the next layer is added.
◍ Legal Forms of Business Organizations.
Answer: 1. Sole Proprietorship: single-person ownership. Simplest form of
ownership2. Partnership: include at least to people to be legal. Partners are
fully responsible for all debts incurred by any one member. A limited
partner is only liable to the extent of his or her investment.3. Corporation:
most complex of the 3 types. Formal meetings must be held for any major
decision.
◍ Head lap, top lap and exposure.
Answer: The 2 inch lap where the shingles are three layers thick is the lead
lap. Top lap is where shingles are at least two layers thick. Head lap is
where shingles are three layers thick.Top Lap = W-E or E+HLHead Lap =
TL -E or W -2EExposure = (W-HL) / 2
◍ How long can a contractor elect to secure a bond or participate in DCA's
Home Improvement Trust Fund?.
Answer: Every 2 years
◍ May a
H. I. Contractor assign the task of getting permits, exemptions or C/O to the
home owner (customer)?.
Answer: No, The prime contractor must secure all necessary permits,
licenses, Certificates of Occupancy, or exemptions necessary to complete
the contract in accordance with state and local building laws.
◍ When ascending or descending a ladder.
Answer: The user shall face the ladder
◍ Fire-resistance rating.
, Answer: Shaft enclosures shall have a fire-resistance rating of not less than 2
hours where connecting four stories or more, not less than 1 hour where
connecting less than four stories.
◍ How many business locations can a
H. I. Contractor's license cover?.
Answer: One. A seperate license is required for each place of business.
◍ Must a subcontractor be seperately licensed by DCA?.
Answer: Yes, this includes electricians and plumbers.
◍ What system installations are part of
H. I.? (4).
Answer: Central heating/air conditioning, Central vacuum, Doors, windows,
awnings, and Communication systems.
◍ Scaffold casters and wheels shall be?.
Answer: Locked with positive wheel and/or wheel and swivel locks, or
equivalent means, to prevent movement of the scaffold while the scaffold is
used on stationary manner.
◍ Horizontal lifelines shall be designed, installed, and used, under the
supervision of a qualified person.
Answer: as part of a complete personal fall arrest system, which maintains a
safety factor of a least two
◍ Who must obtain building and improvement permits?.
Answer: The prime contractor.
◍ Where should quantities of flammable liquid in excess of 25 gallons be
stored in that is acceptable or approved?.
Answer: Acceptable wooden storage and Approved metal storage cabinets.
Cabinets shall be labeled in conspicuous lettering "Flammable-Keep Away
from Open Flames"
◍ Each scaffold unit shall be installed so that the space between adjacent units
and the space between the platform and the uprights is?.