Content preview

FAM 104 Module 3 comprehensive Questions and
Answers with 100% Correct Answers | Latest Version
Question 1.
Sequentially list the phases, decision points, and milestones that are part of presystems
acquisition
Correct Answer: MDD, MSA, Milestone A, TMRR, Preliminary Design Review,
Capability Development Document (CDD) Validation, Development Request for
Proposoal (RFP) Release Decision, Milestone B Preparation

Question 2.
Describe the Materiel Development Decision
Correct Answer: the entry point into the Defense Acquisition System and the Materiel
Solution Analysis phase.

Question 3.
Describe the purpose, content, and importance of the Materiel Solution Analysis Phase
Correct Answer: Purpose: to assess potential materiel solutions and to satisfy the
phase-specific entrance criteria for the next program milestone designated by the
MDA (depending on technology maturity) Content: conduct analysis and other
activities needed to choose the concept for the production to be acquired, to begin
translating valid capability gaps into system-specific requirements including the Key
Performance Parameters (KPPs), and to conduct planning to support decisions on
the acquisition strategy for a product. Importance: This phase helps us access the
affordability of the program and enables us to analyze costs. It facilitates early
systems engineering analysis, threat projections, market research, and sustainment
considerations.

Question 4.
Describe what is reviewed and decided at Milestone A
Correct Answer: At MS A, the MDA approves: 1. The materiel solution determination
2. Plan for TMRR Phase 3. Release of the final RFP 4. Exit criteria to complete TMRR
and enter Engineering and Manufacturing Development(EMD) In order to make the
various approval decisions, the MDA will review a number of documents andother
evidence to ensure the development is ready to proceed: 1. ICD 2. AoA results 3.
Consideration of technological issues 4. Certification requirements and economic
analysis for Major Automated Information Systems (MAIS)

, Question 5.
Describe the purpose, content, and importance of the Technology Maturation and Risk
Reduction Phase
Correct Answer: Purpose: to reduce technology, engineering, integration, and life
cycle cost risk to the point that a decision to contract for EMD can be made with
confidence in successful program execution for development, production, and
sustainment Content: the program manger should conduct risk reduction activities
and ensure technology is mature (Technology Readiness Level 6 or higher

Question 6.
Identify the purpose of the EMD phase and the main work efforts
Correct Answer: Develop, build, and test a material solution to verify requirements
and support production decisions. Work Efforts: 1. Design the system 2. Build the
prototype 3. Test the prototype 4. Prepare for production, deployment, and
sustainment

Question 7.
Explain the purpose of Milestone B
Correct Answer: Entry point to EMD and program initiation

Question 8.
Explain the purpose of the Critical Design Review (CDR)
Correct Answer: The CDR assesses design maturity, design build-to or code-to
documentation, and remaining risks and establishes the initial product baseline. It
will be used as the decision point that the system design is ready to begin
developmental prototype hardware fabrication or software coding with acceptable
risk.

Question 9.
Describe the purpose of Milestone C
Correct Answer: to authorize entry into the P&D phase(limited deployment)

Question 10.
Explain the purpose of the Production and Deployment phase
Correct Answer: to produce and deliver requirements- compliant products toreceiving
military organizations.

Document information

Uploaded on
September 4, 2026
Number of pages
12
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$14.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Favorgrades
3.8
(193)
Sold
830
Followers
376
Items
52691
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions