Spillway pipe for a temporary sediment basin cannot be constructed with a pipe
smaller than _____ inches.
A) 6
B) 8
C) 10
D) 12 - ANSWER -B) 8
What is the amount of over fall allowed at the end of the storm drain outlet apron?
A) 1/2 the diameter of the rip rap used
B) Not to exceed 6 inches
C) 1/2 the thickness of the apron
D) Zero - ANSWER -D) Zero
What size rocks should be used to fill gabion boxes?
A) 3 to 4 inches
B) 4 to 8 inches
C) Larger than 8 inches
D) Clean aggregate - ANSWER -C) Larger than 8 inches
A diversion constructed of compacted soil can be positioned ________ a slope.
A) Above
B) Across
C) Below
D) All of the above - ANSWER -B) Across
A temporary sediment basin's riser pipe must be anchored with a concrete
foundation. The minimum thickness allowed for this foundation is ________
inches.
A) 12
B) 18
C) 24
, D) 32 - ANSWER -B) 18
A temporary down drain structure using a 12 inch pipe could drain up to
________ acres.
A) 0.3
B) 0.5
C) 0.4
D) 1.0 - ANSWER -D) 1.0
A retrofit utilizing a slotted board dam can be used on projects with a larger
drainage area than a retrofit utilizing perforated half round pipe.
A) True
B) False - ANSWER -B) False
A stream channel diversion can only be constructed on streams with a drainage
area less than _________ acres.
A) 830
B) 725
C) 640
D) 500 - ANSWER -C) 640
What may be used to construct a grade stabilization structure?
A) Rock
B) Cement
C) Wood
D) All of the above - ANSWER -D) All of the above
The apron for a storm drain outlet is designed to accommodate the storm water
flow but the minimum length is ______ times the outlet pipe diameter.
A) 4
B) 5
C) 6
D) 8 - ANSWER -C) 6
In jurisdictions where there is a local issuing authority (LIA) one NOI is submitted
to the LIA and a second NOI is submitted to whom?
A) Nation Resource Conservation Service (NRCS)
B) Georgia Soil & Water Conservation Commission (GSWCC)
C) Department of Natural Resources (DNR)