MANAGER EXAM PREP 2026 150 MASTER
SCENARIO Q&AS (WITH IN-LINE
RATIONALE & SMART ANSWERS) -
RATED #1 STUDY GUIDE
NYC DCAS Construction Project Manager Practice Exam
(Questions 1–150)
1. A large-scale public safety facility renovation in Manhattan
experiences a critical structural delay when unforeseen sub-surface
granite is discovered during excavation. As the NYC DCAS
Construction Project Manager, you must initiate a change order.
According to the NYC Procurement Policy Board (PPB) rules, what
is the primary regulatory requirement regarding the justification of
this change order?
• The contractor must absorb the cost under the initial lump-sum
unforeseen contingency clause.
• Correct Answer: The Project Manager must issue a
written determination documenting that the modification
is essential to complete the project scope and that the
price is fair and reasonable.
• The agency must re-bid the entire excavation phase of the project
to ensure competitive market pricing.
• The change order can be approved verbally by the resident
engineer as long as it does not exceed 5% of the base contract.
Rationale: Under NYC PPB rules, change orders require a formal,
written determination by the agency confirming that the work is
necessary, falls within the general scope of the contract, and
represents a fair price based on cost analysis.
2. During a routine safety inspection of a DCAS-managed municipal
office building facade rehabilitation in Brooklyn, you notice
workers on a suspended scaffold without their personal fall arrest
systems (PFAS) secured to independent lifelines. According to NYC
, Department of Buildings (DOB) Chapter 33 regulations, what
immediate action must the Project Manager take?
• Issue a written warning to the site superintendent and re-inspect
the site during the next weekly walkthrough.
• Log the infraction in the daily project diary and notify the prime
contractor's corporate insurance officer.
• Correct Answer: Order an immediate stop-work for the
scaffold operations, ensure workers are safely retrieved,
and issue a safety violation notice to the contractor.
• Request the DOB to send an inspector to site within 48 hours to
evaluate if a Stop Work Order is warranted.
Rationale: Safety infractions involving immediate risk to life,
such as unsecured fall arrest systems on suspended scaffolds
under NYC DOB Chapter 33, mandate immediate stop-work
intervention by management to mitigate the hazard before work
resumes.
3. A contractor submitting a monthly progress payment requisition
under a DCAS line-item contract includes a substantial claim for
stored materials sitting in a warehouse in New Jersey. Which of the
following conditions must be met under standard NYC standard
contract provisions for DCAS to approve payment for these off-site
stored materials?
• The contractor must prove the warehouse is owned by a certified
New York State Minority-owned Business Enterprise (MBE).
• Correct Answer: The materials must be physically
inspected, insured in the City’s name, stored in a secure
bonded warehouse, and explicitly approved by the
Commissioner.
• Off-site stored materials are strictly prohibited from progress
payments until they cross NYC geographic boundaries.
• The contractor only needs to provide a paid invoice from the
manufacturer to receive 100% of the material value.
Rationale: For NYC agencies to pay for off-site stored materials,
the items must be unique or critical, secured in a bonded/insured
facility explicitly naming the City as beneficiary, and verified via
inspection to protect public funds.
,4. You are reviewing a Critical Path Method (CPM) schedule updates
for a multi-floor interior fit-out of a DCAS leasehold space. The
contractor shows that the installation of the HVAC ductwork has a
total float of negative fifteen (-15) days. What does this negative
float value mathematically indicate about the project status?
• The HVAC subcontractor has 15 days of buffer time before they
impact the milestone of the drywall installation.
• The project is running exactly 15 days ahead of its early start
schedule baseline.
• Correct Answer: The project is currently 15 days behind
schedule and will miss its contractually mandated
completion deadline unless corrective action is taken.
• The logic links within the scheduling software have an error,
making the entire network diagram invalid.
Rationale: Negative float in CPM scheduling indicates that the
activities along that path are behind schedule and will delay the
overall project completion date by that exact number of days
unless logic or resources are optimized.
5. A municipal facility roof replacement project requires a
comprehensive hazardous material abatement plan after testing
reveals asbestos-containing materials (ACM) in the flashing.
Which regulatory agency holds primary jurisdiction over the
certification of the workers and the specific air monitoring
protocols inside New York City limits?
• Correct Answer: New York City Department of
Environmental Protection (DEP) under Title 15.
• Federal Occupational Safety and Health Administration (OSHA)
exclusively, superseding local mandates.
• New York State Department of Transportation (NYSDOT).
• New York City Department of Sanitation (DSNY).
Rationale: While federal OSHA sets national baselines, the NYC
DEP strictly regulates asbestos abatement activities, worker
certifications, and air monitoring protocols within New York City
under Title 15 of the Rules of the City of New York.
6. During a concrete pour for a new DCAS maintenance depot garage
floor, the field slump test results show a slump of 7 inches, whereas
, the approved mix design specifies a maximum slump of 4 inches.
The contractor wants to pour anyway, stating they will add extra
cement later. What is your directive?
• Allow the pour to proceed but reduce the contractor's payment line
item by 15% for non-compliance.
• Correct Answer: Reject the concrete truck batch
immediately, stop the pour for that section, and direct
the testing lab to take core samples if any mix was already
placed.
• Accept the concrete but require the contractor to extend the wet
curing period from 7 days to 28 days.
• Instruct the truck driver to spin the drum at high speed for 30
minutes to reduce the water content naturally.
Rationale: Exceeding the maximum specified slump indicates
excess water, which severely compromises the compressive
strength and durability of the concrete. Unapproved field
modifications violate NYC Building Code structural inspections.
7. A DCAS project involving structural steel framing updates for an
administrative annex is subject to "Special Inspections" under the
NYC Building Code. Who must retain and directly pay the
registered Special Inspection Agency to avoid a conflict of interest?
• The general contractor performing the structural steel erection
work.
• The steel fabrication shop supplying the structural beams.
• Correct Answer: The building owner, which in this case is
the City of New York / DCAS agency itself.
• The structural engineer of record out of their professional liability
design fee.
Rationale: The NYC Building Code explicitly mandates that
Special Inspection Agencies must be retained and compensated
directly by the owner (or the City agency managing the asset) to
ensure independent, unbiased quality assurance separate from
the contractor.
8. A project budget variance report shows an Earned Value (EV) of
$450,000, an Actual Cost (AC) of $520,000, and a Planned Value
(PV) of $400,000. What is the Cost Variance (CV) and what does it