◉What does the "P" stand for in the Revised Universal Soil Loss
Equation (RUSLE)?
a. Soil erodibility factor
b. Management operations and support practices (sediment
controls)
c. Rainfall-runoff erosivity factor
d. Length-slope factor
e. Cover factor (erosion controls). Answer: B
◉What is the difference of an LUP project in comparison to
traditional projects?
a. Erosion control is not needed.
b. "Run-On/Run-Off" is not an objective.
c. Sampling is not required.. Answer: B
◉TRUE OR FALSE: The SWPPP is a "living document" that is
amended/updated to reflect conditions & reduce pollutants.
Answer: True
, ◉Stockpiles require a linear sediment barrier at all times, and must
be covered prior to a rain event or when inactive. A stockpile is
inactive after __days of inactivity.
a. 3
b. 7
c. 10
d. 14. Answer: D
◉Once identified, dischargers shall begin implementing repairs or
design changes to BMPs:
a. Immediately
b. Within24 hours
c. Within48 hours
d. ASAP, but not more than 72 hours. Answer: D
◉The discharger shall ensure a QSP develop a Rain Event Action
Plan (REAP) __ hours prior to any likely precipitation event.
a. Immediately
b. 24 hours
c. 48 hours
d. ASAP but not more than 72 hours. Answer: C
QUESTIONS AND VERIFIED ANSWERS
◉What does the "P" stand for in the Revised Universal Soil Loss
Equation (RUSLE)?
a. Soil erodibility factor
b. Management operations and support practices (sediment
controls)
c. Rainfall-runoff erosivity factor
d. Length-slope factor
e. Cover factor (erosion controls). Answer: B
◉What is the difference of an LUP project in comparison to
traditional projects?
a. Erosion control is not needed.
b. "Run-On/Run-Off" is not an objective.
c. Sampling is not required.. Answer: B
◉TRUE OR FALSE: The SWPPP is a "living document" that is
amended/updated to reflect conditions & reduce pollutants.
Answer: True
, ◉Stockpiles require a linear sediment barrier at all times, and must
be covered prior to a rain event or when inactive. A stockpile is
inactive after __days of inactivity.
a. 3
b. 7
c. 10
d. 14. Answer: D
◉Once identified, dischargers shall begin implementing repairs or
design changes to BMPs:
a. Immediately
b. Within24 hours
c. Within48 hours
d. ASAP, but not more than 72 hours. Answer: D
◉The discharger shall ensure a QSP develop a Rain Event Action
Plan (REAP) __ hours prior to any likely precipitation event.
a. Immediately
b. 24 hours
c. 48 hours
d. ASAP but not more than 72 hours. Answer: C