◉ ATS instruments shall record which of the following? Answer:
Flow, turbidity, and pH
◉ Which factor(s) of RUSLE can be based on site-specific analysis
rather than maps? Answer: K and LS
◉ Failure to obtain coverage under the permit for storm water
discharges to waters of the US is a violation of the Answer: Clean
Water Act and California Water Code
◉ For traditional construction projects the LRP may be Answer: The
person who possesses real properly interest in the land upon which
the construction activities will occur for the regulated site
◉ What does NTU measure? Answer: a measurement of optical
properties of a liquid that cause light rays to be scattered and
absorbed rather than transmitted in straight lines through a sample.
, ◉ Inspection Records have to be kept until the project is complete or
three years, whichever comes first. Answer: False
◉ Which factor(s) of RUSLE must be changed to recalculate risk
when the construction duration has changed? Answer: R
◉ BMP stands for Answer: Best Management Practice
◉ Do type 1 LUPs typically have a high potential to impact storm
quality? Answer: No
◉ What does RUSLE stand for? Answer: Revised Universal Soil Loss
Equation
◉ A discharger must notify the Regional Water Boards if there are
planned changes in the construction activity that Answer: May result
in non-compliance
◉ A qualifying storm event is Answer: A rain even that produces 1/2
inch or more of precipitation with a period of 48 hours or more
between rain events.
◉ Continuous monitoring (no less than 15-min intervals) of ATS is
required for: Answer:
QUESTIONS AND ANSWERS 100 PERCENT
CORRECT
◉ ATS instruments shall record which of the following? Answer:
Flow, turbidity, and pH
◉ Which factor(s) of RUSLE can be based on site-specific analysis
rather than maps? Answer: K and LS
◉ Failure to obtain coverage under the permit for storm water
discharges to waters of the US is a violation of the Answer: Clean
Water Act and California Water Code
◉ For traditional construction projects the LRP may be Answer: The
person who possesses real properly interest in the land upon which
the construction activities will occur for the regulated site
◉ What does NTU measure? Answer: a measurement of optical
properties of a liquid that cause light rays to be scattered and
absorbed rather than transmitted in straight lines through a sample.
, ◉ Inspection Records have to be kept until the project is complete or
three years, whichever comes first. Answer: False
◉ Which factor(s) of RUSLE must be changed to recalculate risk
when the construction duration has changed? Answer: R
◉ BMP stands for Answer: Best Management Practice
◉ Do type 1 LUPs typically have a high potential to impact storm
quality? Answer: No
◉ What does RUSLE stand for? Answer: Revised Universal Soil Loss
Equation
◉ A discharger must notify the Regional Water Boards if there are
planned changes in the construction activity that Answer: May result
in non-compliance
◉ A qualifying storm event is Answer: A rain even that produces 1/2
inch or more of precipitation with a period of 48 hours or more
between rain events.
◉ Continuous monitoring (no less than 15-min intervals) of ATS is
required for: Answer: