• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 64 pages
Exam (elaborations)

Dm G+1 Exam Accurate Real Exam Questions And Verified Answers With Detailed Rationales Each | Currently Testing And Frequently Tested Questions | Graded A+

Document preview thumbnail
Preview 4 out of 64 pages

Pass Your Dubai Municipality General Construction Exam with Confidence! This comprehensive practice test features 200+ REAL exam questions with detailed rationales, covering ALL topics tested on the DM G certification. Master Concrete Technology & Formwork, Structural Analysis & Design, Soil Mechanics & Foundations, Construction Management & Safety, and Dubai Building Code Requirements. Updated for 2026/2027 testing and frequently tested content. Each question includes in-depth explanations to reinforce engineering concepts and construction practices. Perfect for civil engineers, site engineers, construction managers, and contractors preparing for Dubai Municipality licensing exams. Mirroring actual exam format, this guide builds test-taking confidence and identifies knowledge gaps. Trusted by thousands for DM certification preparation. Download instantly and start mastering construction engineering today!

Content preview

DM G+1 EXAM ACCURATE REAL EXAM QUESTIONS AND VERIFIED
ANSWERS WITH DETAILED RATIONALES EACH | CURRENTLY TESTING
AND FREQUENTLY TESTED QUESTIONS |
GRADED A+

SECTION 1: CONCRETE TECHNOLOGY AND MATERIALS (Questions 1-40)
1. The shutters and bottom support of a non-cantilever slab can be removed
within a minimum of how many days?
A) 7 days
B) 14 days
C) 21 days
D) 28 days

Answer: B

Rationale: According to Dubai Municipality standards and general construction
practice, the formwork and bottom supports for non-cantilever slabs can be
removed after a minimum of 14 days, provided the concrete has achieved
adequate strength. This allows sufficient time for the concrete to gain strength
and support its own weight.

2. The shutters and bottom support of a non-cantilever beam can be removed
within a minimum of how many days?
A) 7 days
B) 14 days
C) 21 days
D) 28 days

Answer: B

Rationale: For non-cantilever beams, the formwork removal time is similar to
slabs — a minimum of 14 days. The beam must have developed sufficient
strength to carry its own weight and any construction loads.

3. Shotcrete is used in which of the following applications?
A) Repairing surfaces
B) Dam surfaces

1

,C) Curved surfaces
D) All of the above

Answer: D

Rationale: Shotcrete (sprayed concrete) is a versatile material used in repairing
damaged surfaces, constructing dam surfaces, and creating curved surfaces. Its
ability to be applied to vertical and overhead surfaces makes it ideal for these
applications.

4. Bitumen is used in construction to provide:
A) Protective Surface
B) Shining surface
C) Decorative surface
D) All of above

Answer: A

Rationale: Bitumen is primarily used as a protective surface in construction,
especially in waterproofing and road construction. It provides a durable,
waterproof layer that protects structures from moisture and environmental
damage.

5. The first test on concrete is typically done after how many days?
A) 3 days
B) 7 days
C) 14 days
D) 28 days

Answer: B

Rationale: The first compressive strength test on concrete is typically conducted
after 7 days of curing. This provides an early indication of whether the concrete
will achieve its specified 28-day strength.

6. Core samples are taken from concrete structures for finding:
A) Tensile strength
B) Compressive strength

2

,C) Water absorption
D) Surface hardness

Answer: B

Rationale: Core samples are extracted from hardened concrete structures
primarily to determine the compressive strength of the in-place concrete. This is a
common method for assessing the quality and structural integrity of existing
concrete.

7. The Rebound Schmidt hammer test is classified as:
A) Destructive test
B) Non-destructive test
C) Cohesion test
D) All of above

Answer: B

Rationale: The Schmidt hammer (rebound hammer) test is a non-destructive test
used to estimate the compressive strength of concrete. It measures the rebound
of a spring-loaded mass impacting the concrete surface, providing a quick and
easy assessment.

8. Core samples are typically taken after how many days?
A) 7 days
B) 14 days
C) 28 days
D) 10 days

Answer: C

Rationale: Core samples are usually taken after 28 days of curing, as this is the
standard age at which concrete's compressive strength is evaluated. This allows
for a fair comparison with the standard 28-day cube test results.

9. The density of Aluminium is approximately _____ Kg/m3 at normal
temperature.


3

, A) 2500
B) 2700
C) 3500
D) 7800

Answer: B

Rationale: The density of aluminum is approximately 2700 kg/m³. This is
significantly lower than steel (around 7800 kg/m³), making aluminum a
lightweight material suitable for various construction applications.

10. Adding more water to a concrete mix will:
A) Decrease workability
B) Remain same
C) Increase workability
D) No effect

Answer: C

Rationale: Adding more water to a concrete mix increases its workability by
reducing the viscosity of the cement paste. However, this comes at the cost of
reduced strength and durability, as the water-cement ratio increases.

11. The density of AAC (Autoclaved Aerated Concrete) blocks is approximately
_____ Kg/m3.
A) 500
B) 600
C) 700
D) 800

Answer: B

Rationale: AAC blocks have a density of approximately 600 kg/m³. Their
lightweight nature makes them easy to handle and provides excellent thermal
insulation properties.

12. Compaction of concrete is done to:
A) Increase strength

4

Document information

Uploaded on
August 30, 2026
Number of pages
64
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$26.19

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PrepMaster
4.7
(316)
Sold
403
Followers
22
Items
3453
Last sold
19 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions