1. What is the primary purpose of reinforcing steel in a
concrete slab?
A. To increase the concrete's colour uniformity
B. To reduce the amount of cement required
C. To resist tensile stresses and control cracking
D. To make the concrete cure faster
Answer: To resist tensile stresses and control cracking
Rationale: Concrete is strong in compression but
relatively weak in tension. Reinforcing steel helps resist
tensile forces and limits crack widths and propagation.
2. What is the most important reason for properly
consolidating freshly placed concrete?
A. To increase the water content
B. To accelerate evaporation
C. To remove entrapped air and ensure proper contact
around reinforcement and forms
D. To prevent cement hydration
Answer: To remove entrapped air and ensure proper
contact around reinforcement and forms
,Rationale: Proper consolidation eliminates voids and
honeycombing, producing dense concrete with better
strength and durability.
3. What does the water-cement ratio primarily affect?
A. Aggregate color
B. Formwork dimensions
C. Concrete strength and durability
D. Reinforcing-bar diameter
Answer: Concrete strength and durability
Rationale: Excess water generally increases porosity
after curing, reducing strength and durability.
Maintaining the specified water-cement ratio is critical.
4. What is the purpose of a concrete slump test?
A. To determine compressive strength
B. To determine cement content
C. To measure the consistency or workability of fresh
concrete
D. To determine aggregate size
Answer: To measure the consistency or workability of
fresh concrete
Rationale: The slump test provides an indication of
fresh concrete consistency and helps verify that the
delivered concrete is within the specified range.
5. What should be done if concrete begins to stiffen
before placement is complete?
A. Add water without authorization
B. Add soil to the mixture
C. Follow the approved specification and concrete
,supplier's procedure for adjusting workability
D. Add additional aggregate
Answer: Follow the approved specification and concrete
supplier's procedure for adjusting workability
Rationale: Unauthorized water addition can increase the
water-cement ratio and reduce concrete performance.
Any adjustment must comply with project requirements.
6. What is concrete curing?
A. Removing concrete forms
B. Mixing aggregate with cement
C. Maintaining suitable moisture and temperature
conditions so cement hydration can continue
D. Adding reinforcing steel
Answer: Maintaining suitable moisture and temperature
conditions so cement hydration can continue
Rationale: Proper curing promotes hydration, strength
development, durability, and reduced cracking.
7. What is honeycombing in concrete?
A. Surface discoloration caused by sunlight
B. Excessive cement paste on the surface
C. Voids or rock pockets caused by inadequate
consolidation or poor placement
D. Cracks caused only by freezing
Answer: Voids or rock pockets caused by inadequate
consolidation or poor placement
Rationale: Honeycombing commonly occurs when
concrete does not properly flow around reinforcement
or into form corners and is not adequately consolidated.
, 8. Why should reinforcement be supported on approved
chairs or supports?
A. To make steel easier to paint
B. To reduce concrete temperature
C. To maintain the specified reinforcement position and
concrete cover
D. To increase aggregate size
Answer: To maintain the specified reinforcement
position and concrete cover
Rationale: Reinforcement must remain in its designed
location during concrete placement to provide the
intended structural performance and protection from
corrosion.
9. What is concrete cover?
A. The amount of concrete ordered
B. The thickness of the formwork
C. The distance between the concrete surface and the
nearest reinforcing steel
D. The depth of an excavation
Answer: The distance between the concrete surface and
the nearest reinforcing steel
Rationale: Adequate cover protects reinforcement from
corrosion, fire exposure, and environmental conditions
while helping maintain structural performance.
10. What is the primary purpose of construction joints?
A. To eliminate all concrete movement
B. To increase concrete water content
C. To provide a planned location for stopping and
resuming concrete placement
D. To replace reinforcement