1. What is the primary purpose of construction plans and
specifications?
A. To establish the project's requirements and methods
B. To determine employee wages
C. To replace the contract
D. To eliminate inspections
Rationale: Plans and specifications communicate the design,
materials, dimensions, quality requirements, and construction
requirements for a project.
Correct answer: A. To establish the project's requirements and
methods
2. Which document generally defines the legal obligations
between the owner and contractor?
A. Material receipt
B. Construction contract
C. Daily log
D. Equipment checklist
,Rationale: The construction contract establishes the parties'
responsibilities, scope, payment terms, and other contractual
obligations.
Correct answer: B. Construction contract
3. What is the best first step when reviewing a set of
construction drawings?
A. Begin ordering materials
B. Review the title sheet and general notes
C. Start demolition
D. Prepare payroll
Rationale: General notes and the title sheet provide important
information about the project, drawing organization, codes,
and requirements.
Correct answer: B. Review the title sheet and general notes
4. What does a scale of 1/4 inch = 1 foot mean?
A. 1/4 foot on the drawing equals 1 inch in the field
B. 1/4 inch on the drawing represents 1 foot in actual
construction
C. 1 inch represents 1/4 foot
D. The drawing is full size
Rationale: The scale means each 1/4 inch measured on the
drawing represents 1 actual foot.
,Correct answer: B. 1/4 inch on the drawing represents 1 foot in
actual construction
5. What is a change order?
A. A worker's timecard
B. A modification to the original contract work
C. A material invoice
D. A safety inspection
Rationale: A change order formally modifies the contract
scope, price, schedule, or other terms.
Correct answer: B. A modification to the original contract work
6. What is the main purpose of a jobsite daily log?
A. To document project activities and conditions
B. To replace payroll records
C. To calculate taxes automatically
D. To approve building permits
Rationale: Daily logs provide a record of work performed,
weather, personnel, equipment, deliveries, delays, and
significant events.
Correct answer: A. To document project activities and
conditions
7. Which estimating method provides the greatest detail?
, A. Rough guess
B. Square-foot estimate only
C. Detailed quantity takeoff
D. Verbal estimate
Rationale: A detailed takeoff identifies quantities of labor,
materials, equipment, and other costs required for the work.
Correct answer: C. Detailed quantity takeoff
8. What is a construction contingency primarily intended to
cover?
A. Known employee wages
B. Unforeseen costs or minor uncertainties
C. Contractor profit only
D. Permit numbers
Rationale: Contingency provides a financial allowance for
uncertainties that may arise during construction.
Correct answer: B. Unforeseen costs or minor uncertainties
9. Which cost is normally considered a direct cost?
A. Jobsite concrete materials
B. Corporate office rent
C. General advertising
D. Company-wide accounting