CQM-C FINAL TEST 2026 QUESTIONS
WITH CORRECT ANSWERS GRADED
A+
◍ What is the purpose of CQM?.
Answer: the purpose of CQM is the governments efforts, separate from, but
in coordination and cooperation with the contractor, to assure that the
quality set by the plans and specifications is achieved.
◍ Who said the below?To improve is to change. To be perfect is to change
often. a) Thomas Edisonb) Winston Churchillc) Astronaut Franklin Diazd)
Benjamin Frankline) Albert Einstein.
Answer: b) Winston Churchill
◍ ................. is one of the best skill to survive the rigor of Engineering studies.
a) To have the best communication skillsb) To be an excellent writerc) To
be excellent in Mathematicsd) Master the material taught in previous lecture
before the next lecture arrives.
Answer: d) master the material taught in previous lecture before the next
lecture arrives
◍ Speed reading may work against your learning in your technical courses. a)
Trueb) False.
Answer: a) true
◍ What are the 2 principal areas of CQM activity? Define each.
Answer: •Contractor Quality Control - primary function of the contractor
quality control (CQC) is to assure that the completed project meets alls
quality requirements of the contract. •Government Quality Assurance -
through reviews, inspections, and tests, the Government assures that CQC is
working effectively, and that the product complies with the quality
, established by the contract
◍ False. CQC is principally concerned with control..
Answer: Is the following statement TRUE or FALSE: "CQC is principally
concerned with inspection?" Explain.
◍ ............... is a repetitive process that requires active participation. a)
Mastering Mathematics, Science and Engineeringb) Reading newspaperc)
Watching a movie for entertainmentd) Taking an online class for fun.
Answer: a) mastering mathematics, science and engineering
◍ The purpose of reading in technical courses is ...................... a) Have enough
knowledge to impress professor during the lectureb) Finish reading one
chapter per hour.c) To be able to solve problems as fast as possibled) Have
knowledge of principles to be able to solve numerical or analytical
problems.
Answer: d) have knowledge of principles to be able to solve numerical or
analytical problems
◍ Contractor benefits from effective CQC.
Answer: •reduces tear out and replacement cost stemming from deficient
workmanship and materials•causes work to be done the first time•greater
profits•improves reputation and leads to more jobs•improved safety, which
means less lost time and insurance claims•Pride in delivery of a quality
product
◍ Name the items upon which partnering relationships are based.
Answer: Trust, dedication to common goals, understand and assitance to
reach other individual expectations and values
◍ Design Variation Clarification Request (DVCR).
Answer: is a structured workflow for identifying, reviewing, approving, and
documenting changes to the original project design or specifications.
◍ ..................... is not a related question to the chapter subsection with title
"What should you do before you read?" a) What are some of the distractions
that may happen when I read for comprehension?b) What are the benefits of
, doing things to prepare myself before reading?c) How can I improve my
listening skills?d) What do I need to learn before I read?.
Answer: c) how can I improve my listening skills?
◍ Prior to government approval.
Answer: design change by the contractor must be done when?
◍ In engineering technical courses, when reading for comprehension, the best
approach is to lay in an easy chair and read the book as you would like a
Charles Dickens novel. a) Trueb) False.
Answer: b) false
◍ After government approval.
Answer: variation by the contractor must be considered when?
◍ While you are reading for comprehension in technical and engineering
courses, .................... a) Focus on exercises and problems only.b) Try to
read quickly, so you can cover as much material as possible.c) Periodically
stop reading and recite what you have read.d) Try to get to homework
problems as quickly as possible.
Answer: c) periodically stop reading and recite what you have read
◍ • Site conditions and restraints: Check for proper utility interface with
existing facilities. Verify locations of utilities in the facility, waste disposal,
site location, site survey control point, etc.•Proper allowance for
maintenance space and access: The contractor shall prepare layout drawings
of equipment to assure that adequate maintenance access has been
provided.•Conflicts and discrepancies between plans and specifications..
Answer: Name some possible areas that must be addressed during the
construction coordination review of plans and specifications.
◍ Names & Qualifications of ALL QC personnel (To include QC Specialist
and area of specialty).
Answer: Something that should be on the quality control plan.
◍ Preparatory Phase.
Answer: •before a DFOW starts - Agree on•Quality
WITH CORRECT ANSWERS GRADED
A+
◍ What is the purpose of CQM?.
Answer: the purpose of CQM is the governments efforts, separate from, but
in coordination and cooperation with the contractor, to assure that the
quality set by the plans and specifications is achieved.
◍ Who said the below?To improve is to change. To be perfect is to change
often. a) Thomas Edisonb) Winston Churchillc) Astronaut Franklin Diazd)
Benjamin Frankline) Albert Einstein.
Answer: b) Winston Churchill
◍ ................. is one of the best skill to survive the rigor of Engineering studies.
a) To have the best communication skillsb) To be an excellent writerc) To
be excellent in Mathematicsd) Master the material taught in previous lecture
before the next lecture arrives.
Answer: d) master the material taught in previous lecture before the next
lecture arrives
◍ Speed reading may work against your learning in your technical courses. a)
Trueb) False.
Answer: a) true
◍ What are the 2 principal areas of CQM activity? Define each.
Answer: •Contractor Quality Control - primary function of the contractor
quality control (CQC) is to assure that the completed project meets alls
quality requirements of the contract. •Government Quality Assurance -
through reviews, inspections, and tests, the Government assures that CQC is
working effectively, and that the product complies with the quality
, established by the contract
◍ False. CQC is principally concerned with control..
Answer: Is the following statement TRUE or FALSE: "CQC is principally
concerned with inspection?" Explain.
◍ ............... is a repetitive process that requires active participation. a)
Mastering Mathematics, Science and Engineeringb) Reading newspaperc)
Watching a movie for entertainmentd) Taking an online class for fun.
Answer: a) mastering mathematics, science and engineering
◍ The purpose of reading in technical courses is ...................... a) Have enough
knowledge to impress professor during the lectureb) Finish reading one
chapter per hour.c) To be able to solve problems as fast as possibled) Have
knowledge of principles to be able to solve numerical or analytical
problems.
Answer: d) have knowledge of principles to be able to solve numerical or
analytical problems
◍ Contractor benefits from effective CQC.
Answer: •reduces tear out and replacement cost stemming from deficient
workmanship and materials•causes work to be done the first time•greater
profits•improves reputation and leads to more jobs•improved safety, which
means less lost time and insurance claims•Pride in delivery of a quality
product
◍ Name the items upon which partnering relationships are based.
Answer: Trust, dedication to common goals, understand and assitance to
reach other individual expectations and values
◍ Design Variation Clarification Request (DVCR).
Answer: is a structured workflow for identifying, reviewing, approving, and
documenting changes to the original project design or specifications.
◍ ..................... is not a related question to the chapter subsection with title
"What should you do before you read?" a) What are some of the distractions
that may happen when I read for comprehension?b) What are the benefits of
, doing things to prepare myself before reading?c) How can I improve my
listening skills?d) What do I need to learn before I read?.
Answer: c) how can I improve my listening skills?
◍ Prior to government approval.
Answer: design change by the contractor must be done when?
◍ In engineering technical courses, when reading for comprehension, the best
approach is to lay in an easy chair and read the book as you would like a
Charles Dickens novel. a) Trueb) False.
Answer: b) false
◍ After government approval.
Answer: variation by the contractor must be considered when?
◍ While you are reading for comprehension in technical and engineering
courses, .................... a) Focus on exercises and problems only.b) Try to
read quickly, so you can cover as much material as possible.c) Periodically
stop reading and recite what you have read.d) Try to get to homework
problems as quickly as possible.
Answer: c) periodically stop reading and recite what you have read
◍ • Site conditions and restraints: Check for proper utility interface with
existing facilities. Verify locations of utilities in the facility, waste disposal,
site location, site survey control point, etc.•Proper allowance for
maintenance space and access: The contractor shall prepare layout drawings
of equipment to assure that adequate maintenance access has been
provided.•Conflicts and discrepancies between plans and specifications..
Answer: Name some possible areas that must be addressed during the
construction coordination review of plans and specifications.
◍ Names & Qualifications of ALL QC personnel (To include QC Specialist
and area of specialty).
Answer: Something that should be on the quality control plan.
◍ Preparatory Phase.
Answer: •before a DFOW starts - Agree on•Quality