• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 45 pages
Exam (elaborations)

EVM 101 Fundamentals of Earned Value Management Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationale 2027 Q&A| Instant Download Pdf.

Document preview thumbnail
Preview 4 out of 45 pages

EVM 101 Fundamentals of Earned Value Management Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationale 2027 Q&A| Instant Download Pdf.

Content preview

EVM 101 Fundamentals of Earned Value
Management Exam Practice Questions
And Correct Answers (Verified Answers)
Plus Rationale 2027 Q&A| Instant
Download Pdf.



1. The primary purpose of Earned Value Management (EVM) is to:

A. Integrate scope, schedule, and cost performance measurement
B. Replace all project management processes
C. Eliminate the need for budgets
D. Focus only on financial reporting

Answer: A

Rationale: EVM integrates scope, schedule, and cost data to provide
objective measurement of project performance.

2. Earned Value Management compares:

,A. Planned work, completed work, and actual costs
B. Employee performance and salaries
C. Contract terms and vendor selection
D. Design quality and production rates

Answer: A

Rationale: EVM evaluates performance by comparing what was planned,
what was accomplished, and what was spent.

3. Planned Value (PV) represents:

A. The authorized budget for scheduled work at a specific point in time
B. The actual cost of completed work
C. The value of completed work
D. The remaining project budget

Answer: A

Rationale: Planned Value is the approved budget assigned to work
scheduled to be completed by a certain date.

4. Earned Value (EV) represents:

A. The budgeted value of work actually completed
B. The amount of money spent

,C. The total project budget
D. The remaining available funds

Answer: A

Rationale: Earned Value measures completed work using its planned
budget value.

5. Actual Cost (AC) represents:

A. The real cost incurred for completed work
B. The planned budget for future work
C. The value of unfinished work
D. The authorized project reserve

Answer: A

Rationale: Actual Cost reflects the resources actually consumed to perform
the work.

6. The formula for Schedule Variance (SV) is:

A. EV − PV
B. EV − AC
C. PV − EV
D. AC − EV

Answer: A

, Rationale: Schedule Variance compares earned progress against planned
progress.

7. The formula for Cost Variance (CV) is:

A. EV − AC
B. PV − EV
C. AC − PV
D. EV − PV

Answer: A

Rationale: Cost Variance determines whether completed work cost more or
less than planned.

8. A positive Schedule Variance indicates:

A. More work has been completed than planned
B. The project is behind schedule
C. Costs exceed the budget
D. The project is complete

Answer: A

Rationale: Positive SV means earned value exceeds planned value,
indicating ahead-of-schedule performance.

9. A negative Cost Variance indicates:

Document information

Uploaded on
August 24, 2026
Number of pages
45
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$24.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
YouTubes
3.6
(37)
Sold
220
Followers
2
Items
5515
Last sold
17 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions