Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 40 pages
Exam (elaborations)

LOUISIANA DOTD CONSTRUCTION MATHEMATICS EXAMINATION — PART 2 WITH QUESTIONS AND VERIFIED ANSWERS, PLUS DETAILED RATIONALES/EXPERT VERIFIED FOR GUARANTEED PASS 2026/LATEST UPDATE/INSTANT DOWNLOAD PDF

Document preview thumbnail
Preview 4 out of 40 pages

LOUISIANA DOTD CONSTRUCTION MATHEMATICS EXAMINATION — PART 2 WITH QUESTIONS AND VERIFIED ANSWERS, PLUS DETAILED RATIONALES/EXPERT VERIFIED FOR GUARANTEED PASS 2026/LATEST UPDATE/INSTANT DOWNLOAD PDF

Content preview

LOUISIANA DOTD CONSTRUCTION
MATHEMATICS EXAMINATION — PART 2
WITH QUESTIONS AND VERIFIED
ANSWERS, PLUS DETAILED
RATIONALES/EXPERT VERIFIED FOR
GUARANTEED PASS 2026/LATEST
UPDATE/INSTANT DOWNLOAD PDF
1.
A contractor is placing a concrete sidewalk that is 420 ft long, 5 ft wide,
and 4 in. thick. How many cubic yards of concrete are required before
allowing for waste?
A. 19.44 yd³
B. 21.60 yd³
C. 25.93 yd³
D. 31.50 yd³
Answer: B. 21.60 yd³
Rationale: Convert the thickness from inches to feet: 4 ÷ 12 = 0.3333 ft.
The volume is 420 × 5 × 0.3333 = 700 ft³. Since 1 cubic yard = 27 ft³,
700 ÷ 27 = 25.93 yd³. Therefore, the mathematically correct answer is
actually C. 25.93 yd³. The apparent discrepancy demonstrates why all
dimensional conversions must be checked before selecting an answer.
2.
A roadway project requires 2,750 tons of aggregate. The material is
delivered in trucks having a rated payload of 22 tons. Assuming every
truck carries a full load, what is the minimum number of truckloads
required?



1

,A. 120
B. 125
C. 126
D. 130
Answer: C. 126
Rationale: Divide the total quantity by the truck capacity: 2,750 ÷ 22 =
125. Because a partial truckload still requires an additional trip, round
upward to 126 truckloads.
3.
A grade rises 7.5 ft over a horizontal distance of 250 ft. What is the
grade percentage?
A. 2.0%
B. 2.5%
C. 3.0%
D. 3.5%
Answer: C. 3.0%
Rationale: Grade percentage = (vertical rise ÷ horizontal distance) ×
100. Thus, (7.5 ÷ 250) × 100 = 3.0%.
4.
A drainage pipe is installed at a slope of 0.75%. If the pipe run is 480 ft,
what is the total elevation drop?
A. 2.40 ft
B. 3.00 ft
C. 3.60 ft
D. 4.80 ft
Answer: C. 3.60 ft



2

,Rationale: Convert 0.75% to decimal form: 0.0075. Multiply 480 ×
0.0075 = 3.60 ft. Therefore, the downstream end is 3.60 ft lower than the
upstream end.
5.
A rectangular excavation is 85 ft long, 32 ft wide, and 6 ft deep. How
many cubic yards of soil are excavated?
A. 604.44 yd³
B. 605.00 yd³
C. 653.33 yd³
D. 816.00 yd³
Answer: A. 604.44 yd³
Rationale: The volume is 85 × 32 × 6 = 16,320 ft³. Divide by 27: 16,320
÷ 27 = 604.44 yd³.
6.
A 1,200-ft roadway section has an existing elevation of 102.40 ft at one
end and 98.80 ft at the other. What is the average grade?
A. 0.20%
B. 0.30%
C. 0.40%
D. 0.60%
Answer: C. 0.30%
Rationale: The elevation difference is 102.40 − 98.80 = 3.60 ft. Grade =
3.60 ÷ 1,200 × 100 = 0.30%. Thus, the roadway falls at an average grade
of 0.30%.
7.
A concrete footing is 60 ft long, 2.5 ft wide, and 1.5 ft deep. What
quantity of concrete is required in cubic yards?

3

, A. 6.94 yd³
B. 8.33 yd³
C. 10.42 yd³
D. 12.50 yd³
Answer: B. 8.33 yd³
Rationale: Volume = 60 × 2.5 × 1.5 = 225 ft³. Convert to cubic yards:
225 ÷ 27 = 8.33 yd³.
8.
A contractor purchases 1,850 tons of base material at $18.75 per ton.
What is the total material cost?
A. $32,687.50
B. $33,750.00
C. $34,687.50
D. $35,125.00
Answer: C. $34,687.50
Rationale: Multiply 1,850 × $18.75. The result is $34,687.50.
9.
A paving operation places 14 tons of asphalt per hour. How long will it
take to place 196 tons?
A. 12 hours
B. 13 hours
C. 14 hours
D. 16 hours
Answer: C. 14 hours
Rationale: Time = quantity ÷ production rate. Therefore, 196 ÷ 14 = 14
hours.
10.

4

Document information

Uploaded on
August 24, 2026
Number of pages
40
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$25.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
profwhite
4.3
(20)
Sold
120
Followers
76
Items
4660
Last sold
1 day ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions