100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

Summary for A2

Puntuación
-
Vendido
2
Páginas
4
Grado
B
Subido en
10-07-2021
Escrito en
2020/2021

This is a very summarised set of notes needed for the A2. It is summarised in such a way that it will be easy to remember and build own definitions during the exam

Institución
Grado








Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Libro relacionado

Escuela, estudio y materia

Institución
Grado

Información del documento

Subido en
10 de julio de 2021
Número de páginas
4
Escrito en
2020/2021
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

included in project WBS
CHAPTER 8 CHAPTER 9
How to calculate: Activities in project closure Think as if I was selling notes
{Actual cost (AC)} 1. ALL work is completed
Actual amount of money spent at any given time/ actual costs to date 2. Notifying + delivery
3. Acceptance of delivery
AC=ALL costs incurred up to that date 4. Documentation is complete + closure report.
4.1 Pm will make a checklist
{PLANNED VALUE (PV)} 4.1 Start with project closure report
Rand value 4.1 Storing project records
PV= cost per month/day/year × N! of days completed 5. Payment Project team members
materials
6. Redistribute resources equipment
7. Close contracts (e.g ext. suppliers) w/legal counsel
{EARNED VALUE (EV)} 8. (NDA’s)
EV= % work completed × total cost of project OR #units completed x cost per unit 9. Keep OR not to keep records?
10. Documents stored safely + transfer manuals, training materials to client
11. Product support requirements after sale
INTERPRETING CV(EV-AC) 12. Closing financial books
Positive CV à under budgetà we have spent
{ EV/AC = …% } less budget than anticipated Project handover activities
negative CV à over budget à we have spent 1. Document handover + requirements
2. Transition document (includes a suggest maintenance team)
{ EV/AC = …% } more budget than anticipated - Area [setup]
CV=0 à on budget - Operations manual
- Sign of acceptance
- Lessons learned
INTERPRETING SV(EV-PV) 3. Training end users
4. Transfer of manuals to end user
Positive SV à ahead of schedule à we are ahead of schedule.
We have performed { EV/PV = …% } of the work planned Project benefits
negative SV à behind of schedule à we are behind schedule. The project manager is ultimately
Financial benefits: Non-Financial benefits
We have performed { EV/PV = …% } of the work planned Business objective i.t.o: VA to a business from a for ensuring all deliverable are
- Revenue project. Must be tangible + achieved for project success. After
SV=0 à on schedule - Contribution
- Profit enhancement
measurable: the sponsor is notified
- Operational performance
- Savings in operating - Process performance
costs/working capital - Client satisfaction
GRAPHING: - Performance indicators
à if EV curve lies above AC à cost variance is positiveà underbudget
à if EV curve lies below AC à cost variance is negative à overbudget how do you know if a project was successful?
à if EV curve lies above PV à schedule variance is positive à ahead of schedule 1. Efficiency: did the project meet their budget + schedule?
à if EV curve lies below PV à schedule variance is negative à behind schedule 2. Client impact/satisfaction: technical + operation specification? Meet customer needs?
3. Business/direct success: commercial success? ­ market share?
4. Future potential: presence in the market? Develop new 1. technology?
Components in project closure
1. Closure activities
2. Handover
3. Benefits realization
4. Follow-on-actions + recommendation
5. Formal sign-off & acceptance
6. Project evaluation
$5.17
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
mackenziepotter

Conoce al vendedor

Seller avatar
mackenziepotter University of Cape Town
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
4
Miembro desde
7 año
Número de seguidores
3
Documentos
3
Última venta
7 meses hace

0.0

0 reseñas

5
0
4
0
3
0
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes