What are the phases of the Project c. define, plan, execution, close
Life Cycle?
a. scope, budget, time
b. budget, plan, execution, close
c. define, plan, execution, close
What is triple constraint? a. scope, budget, schedule
a. scope, budget, schedule
b. define, plan, execute
c. balance, tradeoff,
communication
What is an example of information c. risks to the project
that might be found in a project A complete project proposal includes any
proposal? risks that
a. Low-level estimate of the costs might derail the project.
b. Project charter
c. Risks to the project
, What concludes the project a. Creation of the project charter
defining c. Selection of the project
phase? (Choose all that apply.)
a. Creation of the project charter
b. Creation of a work breakdown
structure
c. Selection of the project
d. Brainstorming approaches for
getting key stakeholders on board
Major project outcomes and b. project proposal
deliverables, how the project will Major project outcomes and deliverables,
be how the
completed, and a high-level project will be completed, and a high-level
estimate estimate of the cost and completion time
of the cost and completion time are
are included in the project proposal.
included in the _____.
a. project concept document
b. project proposal
c. project charter
When does the project defining a. When an idea for a project is identified
phase begin? by a
a. When an idea for a project is company
identified by a company The defining phase begins when an idea
b. When the project charter is for a
drafted project is identified.
c. When all aspects of the triple
constraints are met
d. When management decides to
select a project for implementation
Modules 10, 11 Exam Questions and
Answers with Verified Solutions | Latest
Updated 2026
What are the phases of the Project c. define, plan, execution, close
Life Cycle?
a. scope, budget, time
b. budget, plan, execution, close
c. define, plan, execution, close
What is triple constraint? a. scope, budget, schedule
a. scope, budget, schedule
b. define, plan, execute
c. balance, tradeoff,
communication
What is an example of information c. risks to the project
that might be found in a project A complete project proposal includes any
proposal? risks that
a. Low-level estimate of the costs might derail the project.
b. Project charter
c. Risks to the project
, What concludes the project a. Creation of the project charter
defining c. Selection of the project
phase? (Choose all that apply.)
a. Creation of the project charter
b. Creation of a work breakdown
structure
c. Selection of the project
d. Brainstorming approaches for
getting key stakeholders on board
Major project outcomes and b. project proposal
deliverables, how the project will Major project outcomes and deliverables,
be how the
completed, and a high-level project will be completed, and a high-level
estimate estimate of the cost and completion time
of the cost and completion time are
are included in the project proposal.
included in the _____.
a. project concept document
b. project proposal
c. project charter
When does the project defining a. When an idea for a project is identified
phase begin? by a
a. When an idea for a project is company
identified by a company The defining phase begins when an idea
b. When the project charter is for a
drafted project is identified.
c. When all aspects of the triple
constraints are met
d. When management decides to
select a project for implementation