Question 1
What is an important best practice you should communicate to the Design team about the
formatting of the spec book?
a. The table of contents should be in the first 20 pages of the spec book
b. The spec section number and description should be in the header and footer of every
page
c. There should not be any text that looks like a spec section number in the header or footer
of the page
d. All of the above
CORRECT ANSWER
d. All of the above
Question 2
True or False: To upload a revision to your spec book, you will first need to delete the old
version from Procore.
CORRECT ANSWER
False
Question 3
Why are some action buttons inactive and gray?
CORRECT ANSWER
Because certain actions require that you first select one or more spec sections before the
button becomes orange/clickable
1
@https://www.stuvia.com/user/thestudyvault
, Question 4
In Procore, what does it mean if there is a blue caret in a field?
CORRECT ANSWER
The field is editable in-line
Question 5
True or False: If you have a project with more than one building or area, you should enable
the "Drawings by Area" feature.
CORRECT ANSWER
True
Question 6
True or False: When you click a project's Drawings tool, you should expect to see the
project's "current set" of drawings. (i.e. The most recently uploaded revisions of each
drawing.)
CORRECT ANSWER
True
Question 7
If you see this icon next to a drawing, what does it mean?
square & triangle
CORRECT ANSWER
The drawing contains manually added markups
2
@https://www.stuvia.com/user/thestudyvault
What is an important best practice you should communicate to the Design team about the
formatting of the spec book?
a. The table of contents should be in the first 20 pages of the spec book
b. The spec section number and description should be in the header and footer of every
page
c. There should not be any text that looks like a spec section number in the header or footer
of the page
d. All of the above
CORRECT ANSWER
d. All of the above
Question 2
True or False: To upload a revision to your spec book, you will first need to delete the old
version from Procore.
CORRECT ANSWER
False
Question 3
Why are some action buttons inactive and gray?
CORRECT ANSWER
Because certain actions require that you first select one or more spec sections before the
button becomes orange/clickable
1
@https://www.stuvia.com/user/thestudyvault
, Question 4
In Procore, what does it mean if there is a blue caret in a field?
CORRECT ANSWER
The field is editable in-line
Question 5
True or False: If you have a project with more than one building or area, you should enable
the "Drawings by Area" feature.
CORRECT ANSWER
True
Question 6
True or False: When you click a project's Drawings tool, you should expect to see the
project's "current set" of drawings. (i.e. The most recently uploaded revisions of each
drawing.)
CORRECT ANSWER
True
Question 7
If you see this icon next to a drawing, what does it mean?
square & triangle
CORRECT ANSWER
The drawing contains manually added markups
2