Term
Which of the following statements regarding critical paths is true?
A. Some activities on the critical path may have slack.
В. The shortest of all paths through the network is the critical path.
C. Every network has only one critical path.
D. The duration of the critical path is the average duration of all paths in
the project network.
E. On a specific project, there can be multiple critical paths, all with
exactly the same duration.
Give this one a try later!
E. Exponential smoothing typically E. On a specific project, there
requires less record keeping of past can be multiple critical paths, all
data. with exactly the same duration.
, D. It is based on the assumption that
A. Only critical activities contribute to
the analysis of past demand helps
the project variance.
predict future demand
Don't know?
2 of 22
Term
A fundamental distinction between trend projection and linear
regression is that:
A. trend projection uses two smoothing constants, not just one.
B. in trend projection the independent variable is time; in linear
regression the independent variable need not be time, but can be any
variable with explanatory power.
C. trend projection can be a function of several variables, while linear
regression can only be a function of one variable.
D. only linear regression can have a negative slope.
E. trend projection uses least squares while linear regression does not.
Give this one a try later!
B. in trend projection the independent variable is time; in linear regression the
independent variable need not be time, but can be any variable with
explanatory power.
D. It is based on the assumption that the analysis of past demand helps predict
future demand
, E. Exponential smoothing typically requires less record keeping of past data.
b. Crashing shortens the project duration by assigning more resources to one or
more of the critical tasks.
Don't know?
3 of 22
Term
The ability of an organization to produce goods or services that have
some uniqueness in their characteristics is:
A. competing on productivity.
B. mass production.
С. competing on quality.
D. competing on differentiation.
E. time-based competition.
Give this one a try later!
D. decreasing inputs while holding
D. competing on differentiation.
outputs steady.
B. introduction, growth, maturity, and
D. experience differentiation.
decline.
Don't know?
ANSWERS
Correct 22
Incorrect 00
1 of 22
Term
Which of the following statements regarding critical paths is true?
A. Some activities on the critical path may have slack.
В. The shortest of all paths through the network is the critical path.
C. Every network has only one critical path.
D. The duration of the critical path is the average duration of all paths in
the project network.
E. On a specific project, there can be multiple critical paths, all with
exactly the same duration.
Give this one a try later!
E. Exponential smoothing typically E. On a specific project, there
requires less record keeping of past can be multiple critical paths, all
data. with exactly the same duration.
, D. It is based on the assumption that
A. Only critical activities contribute to
the analysis of past demand helps
the project variance.
predict future demand
Don't know?
2 of 22
Term
A fundamental distinction between trend projection and linear
regression is that:
A. trend projection uses two smoothing constants, not just one.
B. in trend projection the independent variable is time; in linear
regression the independent variable need not be time, but can be any
variable with explanatory power.
C. trend projection can be a function of several variables, while linear
regression can only be a function of one variable.
D. only linear regression can have a negative slope.
E. trend projection uses least squares while linear regression does not.
Give this one a try later!
B. in trend projection the independent variable is time; in linear regression the
independent variable need not be time, but can be any variable with
explanatory power.
D. It is based on the assumption that the analysis of past demand helps predict
future demand
, E. Exponential smoothing typically requires less record keeping of past data.
b. Crashing shortens the project duration by assigning more resources to one or
more of the critical tasks.
Don't know?
3 of 22
Term
The ability of an organization to produce goods or services that have
some uniqueness in their characteristics is:
A. competing on productivity.
B. mass production.
С. competing on quality.
D. competing on differentiation.
E. time-based competition.
Give this one a try later!
D. decreasing inputs while holding
D. competing on differentiation.
outputs steady.
B. introduction, growth, maturity, and
D. experience differentiation.
decline.
Don't know?