Louisiana Residential Contractors License
Study online at https://quizlet.com/_ezm8lj
1. What is the minimum compressive strength in psi for 2,500 PSI
a concrete basement slab with negligible weathering
potential?
2. An accessory structure is a structure not greater than 3,000 SF
_______ SF
3. What is the R Value insulation requirement for a resi- 19
dential floor climate zone 3?
4. For a "Means of Egress Door", what is the minimum 32''
width of each door opening in inches?
5. Exterior wood framing walls shall be a minimum of 3
_____ grade wood.
6. Which of the following is not considered work exempt Fences less than 6 ft
from a permit?
Swings/Playground equipment
Sidewalks
Fences less than 6ft
interior painting
7. A permit becomes invalid if the work authorized by the 180 days
permit does not begin in ____ days.
8. True or False the building Permit should be kept onsite True
until work is complete?
9. When shall a final inspection be conducted? After permitted work is
complete.
10. What is Required in a certificate of occupancy? Name and Address of
Owner
, Louisiana Residential Contractors License
Louisiana Residential Contractors License
Study online at https://quizlet.com/_ezm8lj
Name of Building Official
Edition of the code permit
was issued under
11. Which is required on a site plan? Traffic Control Plan
-location of new construction
- distance from lot lines
-traffic control plan
-location of existing structures
12. How long must you retain approved construction doc- 180 days
uments after the work is completed?
13. Who is authorized to establish a refund policy for per- Building Official
mit fees?
14. True or False You are allowed to continue work safely False
after a stop work order has been issued?
15. Who appoints the building official from the depart- Chief Appointing Authority
ment of building safety? of the Jurisdiction
16. When there is a conflict and different sections of the Use the most restrictive
IBC specify different materials you must? guidence
17. Live loads for floors and roofs must be posted by the 50 PSF
owner when they exceed _______PSF
18. A Permit is not valid until? The fee has been paid
19. Who has the authority to authorize temporary utility Building Official
connections?
20. False