Term Definition
ProjectLibre can do its E.
scheduling from ________.
a. the project start date
b. the project stop date
c. the project initiate date
d. All of the alternatives are
correct.
e. Only a. and b. are correct
Give this one a try later!
True False
, 2 of 132
Term Definition
According to Larson and Gray B.
chapter 8, project network times
are not a schedule until ________.
a. budgets have been time-
phased
b. resources have been
assigned
c. costs have been determined
d. All of these alternatives are
correct.
e. Only a. and c. are correct.
Give this one a try later!
True False
3 of 132
Term Definition
In ProjectLibre, by default any C.
link between tasks (activities) is
assumed to be ________.
,a. Finish-to-Finish
b. Start-to-Start
c. Finish-to-Start
d. Start-to-Finish
e. There is no default setting in
ProjectLibre.
Give this one a try later!
True False
4 of 132
Term Definition
Which of the following
D.
statements is false?
a. A resource breakdown
structure is a hierarchical
structure that identifies the
project's resources by category
and type.
b. Duration and effort are
synonymous terms.
c. A three-point estimate in PERT
, includes an optimistic, a most
likely, and a pessimistic estimate.
d. A Gantt chart is a common
tool for displaying project
schedule information on a
timeline.
e. Both b. and d. are false
statements.
Give this one a try later!
True False
Correct definition
B.
5 of 132
Term Definition
The implication of the cost of
B.
quality taxonomy discussed in
class was to ________.
a. spend more money on
appraisal so as to incur less in
the way of external costs due to
bugs and software defects
Term Definition
ProjectLibre can do its E.
scheduling from ________.
a. the project start date
b. the project stop date
c. the project initiate date
d. All of the alternatives are
correct.
e. Only a. and b. are correct
Give this one a try later!
True False
, 2 of 132
Term Definition
According to Larson and Gray B.
chapter 8, project network times
are not a schedule until ________.
a. budgets have been time-
phased
b. resources have been
assigned
c. costs have been determined
d. All of these alternatives are
correct.
e. Only a. and c. are correct.
Give this one a try later!
True False
3 of 132
Term Definition
In ProjectLibre, by default any C.
link between tasks (activities) is
assumed to be ________.
,a. Finish-to-Finish
b. Start-to-Start
c. Finish-to-Start
d. Start-to-Finish
e. There is no default setting in
ProjectLibre.
Give this one a try later!
True False
4 of 132
Term Definition
Which of the following
D.
statements is false?
a. A resource breakdown
structure is a hierarchical
structure that identifies the
project's resources by category
and type.
b. Duration and effort are
synonymous terms.
c. A three-point estimate in PERT
, includes an optimistic, a most
likely, and a pessimistic estimate.
d. A Gantt chart is a common
tool for displaying project
schedule information on a
timeline.
e. Both b. and d. are false
statements.
Give this one a try later!
True False
Correct definition
B.
5 of 132
Term Definition
The implication of the cost of
B.
quality taxonomy discussed in
class was to ________.
a. spend more money on
appraisal so as to incur less in
the way of external costs due to
bugs and software defects