Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 3 fuera de 24 páginas
Examen

ADVANCED PROJECT MANAGEMENT EXAM 1 (PMT 3600V) QUESTIONS AND ANSWERS

Document preview thumbnail
Vista previa 3 fuera de 24 páginas

ADVANCED PROJECT MANAGEMENT EXAM 1 (PMT 3600V) QUESTIONS AND ANSWERS

Vista previa del contenido

ADVANCED PROJECT MANAGEMENT
EXAM 1 (PMT 3600V) QUESTIONS AND
ANSWERS



1. When calculating the Estimate at Completion (EAC) assuming the current budget rate will

continue for the remainder of the project, which formula is used?

A. EAC = AC + Bottom-up ETC


B. EAC = AC + (BAC - EV)


C. EAC = AC + [(BAC - EV) / (CPI * SPI)]


D. EAC = BAC / CPI


Answer: D


Conceptual Explanation: The formula EAC = BAC / CPI is used when the current

cumulative CPI is expected to continue until the end of the project.


2. In a weak matrix organization, who typically holds the most power and authority over the

project budget?

A. The Functional Manager


B. The Project Manager


C. The Project Coordinator

,D. The Project Expeditor


Answer: A


Conceptual Explanation: In a weak matrix, the functional manager maintains most of the

authority, including budget control, while the PM acts more as a coordinator or expeditor.


3. Which of the following best describes the ‘100% Rule’ in the context of a Work Breakdown

Structure (WBS)?

A. Every task must be completed 100% before the next begins.


B. The WBS must include 100% of the work defined by the project scope.


C. The project must have a 100% success rate for all deliverables.


D. Resources must be utilized at 100% capacity throughout the project.


Answer: B


Conceptual Explanation: The 100% Rule states that the WBS represents all product and

project work, including project management; the sum of the work at the child levels must

equal 100% of the work represented by the parent.


4. A project manager is using a technique to estimate activity duration by multiplying the

quantity of work by the labor rate. What is this technique called?

A. Analogous Estimating


B. Three-point Estimating


C. Parametric Estimating

, D. Bottom-up Estimating


Answer: C


Conceptual Explanation: Parametric estimating uses a statistical relationship between

historical data and other variables to calculate an estimate for activity parameters.


5. If an activity has an Early Start (ES) of day 5, a Late Start (LS) of day 10, and a duration of 4

days, what is its Total Float?

A. 1 day


B. 5 days


C. 4 days


D. 15 days


Answer: B


Conceptual Explanation: Total Float is calculated as LS - ES (10 - 5 = 5) or LF - EF.


6. Which quality management tool is specifically used to identify the ‘vital few’ problems

compared to the ‘useful many’?

A. Ishikawa Diagram


B. Control Chart


C. Scatter Diagram


D. Pareto Diagram

Información del documento

Subido en
19 de agosto de 2026
Número de páginas
24
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Thebright
3.6
(44)
Vendido
234
Seguidores
6
Artículos
14496
Última venta
3 semanas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes