with Answers
The 6 concrete cubes are casted and are tested after ____
3 days
7 days
28 days
7 and 28 days
7 and 28 days
Adding more water to concrete mix its workability ____
Decrease
Remain same
Increase
No effect
Increase
Adding more water to concrete mix than its strength ______
Increase
Constant
No relation
Decrease
,Decrease
After 7 days of compressive strength test of cubes what is the minimum value
should be accepted
A: 40%
B: 50%
C: 60%
D: 65%
65%
After how many days can we remove the shuttering of 3.75mx4.75m room slab?
A: 14 days
B: 7 days
C: 28 days
D: 10 days
10 days
Allowable shear strength of concrete depends upon ____
A: tensile strength
B: compressive strength
C: shear strength
D: none
,shear strength
Amount of steel in flat slab is _____ Kg/m3
80-100
200
120
160-185
160-185
As per DM requirements, the yield strength of deformed bars should be ____
N/mm2
A: 260
B: 370
C: 514
D: 460
460
As per DM rule for beams depth more ___shrinkage bars should be used on each
face of beam.
A: 600mm
B: 800mm
C: 760mm
, D: 700mm
700mm
As per DM rules the lap length usually used is _____ for reinforcement.
A: 40d
B: 60d
C: 30d
D: 50d
50d
As per DM tall buildings are those of minimum ______ meter height measured
from ground.
A: 50m
B: 70m
C: 40m
D: 60m,
60m
The Auger boring method is not suitable for _______
A: very hard soil
B: cemented soil
C: very soft soil