Qualification — Local Jurisdiction
Practice Exam 2026 | 100 Questions &
Answers with Detailed Rationales |
Complete Exam Prep & Study Guide
1. During construction, a project manager discovers that a subcontractor's
work conflicts with the approved drawings and specifications. What should
be done FIRST?
A. Allow the subcontractor to continue and correct the work later
B. Issue a payment deduction immediately
C. Stop the affected work, document the conflict, and obtain clarification through
the proper project process
D. Direct the subcontractor to redesign the work
Answer: Stop the affected work, document the conflict, and obtain clarification
through the proper project process
Rationale: Continuing disputed or nonconforming work can increase cost and
liability. The affected work should be controlled while the discrepancy is
,documented and resolved through the approved RFI, architect/engineer, owner,
or change-order process.
2. A construction manager is reviewing a critical-path schedule. An activity has
5 days of total float and experiences a 3-day delay. What is the most likely
immediate effect?
A. The project completion date automatically moves 3 days
B. The activity becomes critical
C. The activity retains 2 days of total float
D. The contractor must submit a change order
Answer: The activity retains 2 days of total float
Rationale: Total float represents the amount of delay an activity can absorb
without delaying the scheduled project completion, assuming the network logic
remains unchanged.
3. Which document normally establishes the contractual requirements for
materials, workmanship, and construction procedures in greater detail than
drawings alone?
A. Daily report
B. Project directory
C. Technical specifications
D. Bid tabulation
Answer: Technical specifications
Rationale: Specifications define detailed requirements for products, materials,
workmanship, execution, testing, and quality standards that supplement the
drawings.
4. A subcontractor submits a request for payment that includes stored
materials. What should the construction manager verify before
recommending payment?
,A. Only the subcontractor's verbal confirmation
B. Ownership, proper storage, documentation, insurance requirements, and
contract eligibility
C. That the materials have been installed
D. That the subcontractor has already been paid by the supplier
Answer: Ownership, proper storage, documentation, insurance requirements,
and contract eligibility
Rationale: Stored-material payments require evidence that the owner receives
an appropriate interest in the materials and that contractual safeguards are
satisfied.
5. What is the primary purpose of a construction submittal?
A. To transfer design responsibility to the contractor
B. To demonstrate that proposed products or methods comply with contract
requirements
C. To replace the construction documents
D. To authorize payment
Answer: To demonstrate that proposed products or methods comply with
contract requirements
Rationale: Submittals allow the design and management team to review
proposed products, equipment, samples, shop drawings, and related
information for conformance with the contract documents.
6. A concrete placement is scheduled during extremely hot weather. Which
concern should receive particular attention?
A. Increasing the water-cement ratio
B. Controlling concrete temperature, evaporation, curing, and placement time
C. Eliminating curing
D. Delaying all testing until the concrete has hardened
, Answer: Controlling concrete temperature, evaporation, curing, and placement
time
Rationale: Hot-weather concreting can accelerate setting and increase
evaporation, increasing the risk of plastic shrinkage, inadequate hydration, and
reduced durability.
7. What is the primary purpose of a construction change-order process?
A. To eliminate the original contract
B. To formally modify contractual scope, price, time, or other requirements
C. To allow verbal instructions to replace written documents
D. To eliminate inspection requirements
Answer: To formally modify contractual scope, price, time, or other
requirements
Rationale: Changes should be documented so that the parties have a clear
record of the revised work, compensation, schedule impact, and contractual
obligations.
8. A contractor claims that an unforeseen site condition will increase costs.
What is the construction manager's best initial response?
A. Automatically approve the claim
B. Reject the claim without investigation
C. Document the condition and compare it with the contract's differing-site-
condition provisions
D. Direct the contractor to absorb all costs
Answer: Document the condition and compare it with the contract's differing-
site-condition provisions
Rationale: Differing-site-condition claims depend on the contract language and
the facts. Documentation, investigation, and comparison with the bid
documents are essential.