1. Before operating a tower crane on a new construction site, which factor
should the operator verify first when reviewing the lift plan?
A. The color of the crane's counterweights
B. The maximum building height
C. The crane's configuration, rated capacity, operating radius, and site
conditions
D. The number of workers assigned to the project
Rationale: The crane configuration and site conditions determine whether the
planned lift can be performed within the manufacturer's rated capacity and
operating limitations.
, 2. A tower crane's load chart indicates 10,000 lb capacity at one radius and
6,500 lb at a greater radius. Why does capacity decrease as radius
increases?
A. The hoist motor becomes less efficient
B. The increased load moment places greater overturning demand on the crane
C. The hook block becomes heavier
D. The boom automatically becomes weaker
Rationale: Load moment is substantially affected by horizontal radius. As radius
increases, the same load produces greater overturning forces and therefore
reduces allowable capacity.
3. During a pre-use inspection, the operator notices a significant crack in a
structural component. What is the appropriate response?
A. Operate at half capacity
B. Monitor it during the shift
C. Weld the crack before operating
D. Remove the crane from service and report the defect for qualified evaluation
Rationale: Structural cracking can compromise crane integrity. The crane should
not be operated until the condition has been evaluated and appropriately
corrected.
4. What is the primary purpose of a tower crane's load moment or rated
capacity indicator?
A. To control wind speed
B. To measure fuel consumption
C. To help prevent operation beyond allowable capacity or load moment
D. To determine the operator's experience level
Rationale: Capacity and load-moment systems provide operational information
and warnings intended to help prevent overload conditions.
, 5. A suspended load begins rotating unexpectedly. What should the operator
generally do?
A. Increase hoisting speed
B. Swing rapidly in the opposite direction
C. Use controlled movements and coordinate with the signalperson to stabilize
the load
D. Release the load immediately
Rationale: Sudden counter-movements can amplify load swing. Controlled crane
movements and proper tag-line or rigging practices are safer.
6. Which condition creates the greatest concern when lifting a load near the
crane's maximum rated capacity?
A. Low ambient temperature alone
B. A combination of large radius, dynamic movement, and uncertain load weight
C. Bright sunlight
D. A newly painted hook
Rationale: Capacity margins can be reduced substantially by radius, dynamic
effects, and inaccurate load-weight information.
7. What does the term "load moment" most directly describe?
A. Hoist speed multiplied by rope diameter
B. Load force multiplied by horizontal distance from the rotation center
C. Boom length divided by load weight
D. Hook height multiplied by wind speed
Rationale: Load moment is commonly represented as force times horizontal
distance. It is fundamental to crane stability and capacity calculations.
8. A tower crane is configured with a longer jib than the configuration used
for a previous lift. What must occur before continuing operations?
A. Only the operator's seat must be adjusted
B. Nothing if the load is unchanged
, C. The crane configuration and applicable load chart must be verified for the
new setup
D. The signalperson must change radios
Rationale: Changing jib configuration can change rated capacities, radii,
counterweight requirements, and operating restrictions.
9. Which situation is most likely to produce side loading of the crane hook?
A. A vertical load directly below the hook
B. Attempting to drag a load horizontally with the hoist
C. A properly centered vertical lift
D. Lowering a free-hanging load vertically
Rationale: Crane hoists are generally designed for vertical lifting. Dragging
loads introduces horizontal forces that can damage components and create
instability.
10.What is the safest initial action when the operator loses visual contact with
the load during a critical lift?
A. Continue because the radio operator can see it
B. Increase speed to complete the lift
C. Stop or hold the load until effective communication and control are restored
D. Lower the load at maximum speed
Rationale: The operator must maintain reliable communication and control
during lifting operations.
11.Why is an accurate determination of load weight important?
A. It determines the crane's color requirements
B. It is necessary to compare the planned load against rated capacity and
operating configuration
C. It determines radio frequency
D. It determines jib paint thickness