1.
During review of a commercial HVAC plan, a mechanical plans examiner
determines that the outdoor-air intake is located too close to a plumbing vent
termination. What is the primary concern?
A. Excessive duct friction
B. Cross-contamination of outdoor air
C. Excessive supply-air temperature
D. Insufficient return-air velocity
Answer: B. Cross-contamination of outdoor air
Rationale: The outdoor-air intake must be positioned to minimize the possibility
of drawing contaminated air from plumbing vents, exhaust outlets, combustion
products, or other pollutant sources into the occupied space.
2.
,A variable-air-volume system serves several offices. At low load, the terminal
units reduce airflow substantially. Which design feature is most important for
maintaining acceptable ventilation?
A. Increasing return-air temperature
B. Maintaining required minimum outdoor airflow
C. Increasing duct velocity
D. Eliminating return-air ducts
Answer: B. Maintaining required minimum outdoor airflow
Rationale: VAV systems can reduce total airflow during part-load operation, but
required ventilation must still be maintained. Controls and terminal-unit
minimums must prevent occupied spaces from receiving inadequate outdoor air.
3.
A mechanical plan specifies a furnace with a listed input of 120,000 Btu/h. The
examiner is reviewing combustion-air provisions. Which factor is most important
in determining the required combustion-air arrangement?
A. Furnace cabinet color
B. Appliance type and installation configuration
C. Supply-duct insulation thickness only
D. Return-air grille size
Answer: B. Appliance type and installation configuration
Rationale: Combustion-air requirements depend on the appliance, fuel, room or
enclosure characteristics, and whether combustion air is provided from the
interior, outdoors, or through engineered systems.
4.
A duct system has an excessively high pressure drop because of numerous sharp
elbows and transitions. Which design change would generally improve system
performance?
,A. Increase the number of abrupt transitions
B. Use smoother fittings and reduce unnecessary resistance
C. Reduce duct size throughout the system
D. Eliminate balancing dampers
Answer: B. Use smoother fittings and reduce unnecessary resistance
Rationale: Excessive fitting resistance increases fan static pressure requirements
and energy consumption. Properly designed transitions, elbows, and branch
connections reduce pressure losses.
5.
A mechanical room contains a gas-fired appliance and is tightly sealed from the
outdoors. What should the examiner evaluate first?
A. Decorative finishes
B. Adequacy of combustion and dilution air
C. Lighting color temperature
D. Ceiling tile pattern
Answer: B. Adequacy of combustion and dilution air
Rationale: A tightly constructed mechanical room may not provide sufficient air
for safe combustion and venting. The plans examiner must verify that the
proposed combustion-air method complies with the applicable requirements.
6.
A supply-air duct passes through a fire-resistance-rated wall. Which item is
generally critical to the review?
A. Paint color
B. Fire damper or approved alternative where required
C. Return grille finish
D. Thermostat height only
Answer: B. Fire damper or approved alternative where required
, Rationale: Penetrations of rated assemblies can compromise fire-resistance
performance. Required dampers, sleeves, firestopping, and listing requirements
must be coordinated with the rated assembly.
7.
A mechanical plan shows a duct penetrating a smoke barrier but does not identify
the damper type. What should the examiner determine?
A. Whether a smoke damper, combination fire-smoke damper, or another
approved protection method is required
B. Whether the duct should be painted
C. Whether the thermostat should be relocated
D. Whether the fan should be removed
Answer: A. Whether a smoke damper, combination fire-smoke damper, or
another approved protection method is required
Rationale: Smoke barriers and fire barriers have different protection
requirements. The plans examiner must identify the assembly and determine the
applicable damper and penetration-protection requirements.
8.
A rooftop HVAC unit is located near the edge of a roof. Which plan-review issue
should receive particular attention?
A. Equipment anchorage and wind resistance
B. Interior wall paint
C. Carpet thickness
D. Office furniture arrangement
Answer: A. Equipment anchorage and wind resistance
Rationale: Rooftop mechanical equipment must be adequately supported and
anchored for applicable structural and environmental loads. Mechanical plans
should coordinate with structural requirements.