Question 1
On the structural layer prior to the friction course, correct any deficiencies before
placing the friction course.
A. Greater than 3/16"
B. Equal to 3/16"
C. Less than 1/8"
D. Greater than 1/8"
Correct Answer
Equal to 3/16"
Question 2
The screed connects to the paver at the _____.
Correct Answer
Tow Point
Question 3
Given: The average sublot density (Gmb) of the roadway cores is 2.223 and the Gmm
for the same sublot is 2.400. The target spread rate was 162 lbs/sq yds. What is the %
of Gmm density for the sublot?
Correct Answer
92.6%
Page 1 of 15
, Question 4
Emptying the hopper between loads can cause the following:
A. Smooth ride
B. Uniform thickness
C. Proper cross-slope
D. All of the above
E. None of the above
Correct Answer
(E.) None of the above
Question 5
A _______ is utilized when attempting to match elevations of two mats placed side by
side
Correct Answer
(D.) Joint Matcher
Question 6
(T/F:) Finish rolling must be completed prior to the mat cooling to 165°F
Correct Answer
True
Question 7
Which condition will result in more time available for compaction?
A. SP-19 coarse mix during the day
B. FC-9.5 fine mix at night
C. FC-9.5 coarse mix during the day
D. SP-12.5 fine mix with PG76-22
Correct Answer
(A.) SP-19 coarse mix during the day
Page 2 of 15
Answers
Question 1
On the structural layer prior to the friction course, correct any deficiencies before
placing the friction course.
A. Greater than 3/16"
B. Equal to 3/16"
C. Less than 1/8"
D. Greater than 1/8"
Correct Answer
Equal to 3/16"
Question 2
The screed connects to the paver at the _____.
Correct Answer
Tow Point
Question 3
Given: The average sublot density (Gmb) of the roadway cores is 2.223 and the Gmm
for the same sublot is 2.400. The target spread rate was 162 lbs/sq yds. What is the %
of Gmm density for the sublot?
Correct Answer
92.6%
Page 1 of 15
, Question 4
Emptying the hopper between loads can cause the following:
A. Smooth ride
B. Uniform thickness
C. Proper cross-slope
D. All of the above
E. None of the above
Correct Answer
(E.) None of the above
Question 5
A _______ is utilized when attempting to match elevations of two mats placed side by
side
Correct Answer
(D.) Joint Matcher
Question 6
(T/F:) Finish rolling must be completed prior to the mat cooling to 165°F
Correct Answer
True
Question 7
Which condition will result in more time available for compaction?
A. SP-19 coarse mix during the day
B. FC-9.5 fine mix at night
C. FC-9.5 coarse mix during the day
D. SP-12.5 fine mix with PG76-22
Correct Answer
(A.) SP-19 coarse mix during the day