1. A landscape contractor is preparing a project proposal for a commercial
property. Which factor should be evaluated first when determining
whether the proposed work can be constructed as designed?
A. The contractor's preferred plant supplier
B. The owner's preferred maintenance schedule
C. Existing site conditions, utilities, grades, drainage, and applicable regulations
D. The anticipated resale value of the property
Answer: Existing site conditions, utilities, grades, drainage, and applicable
regulations
Rationale: Site investigation establishes the physical and regulatory constraints
that control constructability. Ignoring utilities, grades, drainage, or regulations
can result in redesign, damage, delays, and liability.
, 2. Under Iowa contractor registration requirements, which statement is most
accurate for a business performing qualifying construction work?
A. Registration is never required for landscape businesses
B. Registration is required only for businesses with more than 25 employees
C. A qualifying construction contractor generally must register when the
business earns at least $2,000 annually from construction work
D. Registration is required only for public projects
Answer: A qualifying construction contractor generally must register when the
business earns at least $2,000 annually from construction work
Rationale: Iowa requires individual and business construction contractors
performing qualifying construction work to register when they meet the
applicable statutory threshold. Certain exceptions apply, including limited work
on one's own property.
3. Before excavating for a retaining wall, the most important preliminary
safety procedure is to:
A. Begin excavation at the lowest point
B. Saturate the soil to make digging easier
C. Determine the location of underground utilities and establish a safe
excavation plan
D. Remove all nearby vegetation
Answer: Determine the location of underground utilities and establish a safe
excavation plan
Rationale: Utility strikes can cause electrocution, explosions, flooding, service
interruptions, and serious property damage. Utility locating must occur before
excavation.
4. Which soil property most directly controls the ability of a soil to retain and
transmit water?
,A. Soil color alone
B. Organic mulch depth
C. Texture, structure, porosity, and compaction
D. Plant height
Answer: Texture, structure, porosity, and compaction
Rationale: Water movement and storage depend on the distribution of pore
spaces and the physical condition of the soil. Compaction can sharply reduce
infiltration and root-zone aeration.
5. A clay-heavy planting soil has poor infiltration and persistent saturation.
Which improvement is generally most appropriate?
A. Add more fine clay
B. Eliminate all organic matter
C. Improve soil structure through appropriate organic matter management and
reduce compaction
D. Increase irrigation frequency
Answer: Improve soil structure through appropriate organic matter
management and reduce compaction
Rationale: Increasing irrigation in poorly drained soil can worsen saturation.
Appropriate organic matter and reduced compaction can improve aggregation,
pore structure, and infiltration.
6. When planting a balled-and-burlapped tree, the root flare should generally
be:
A. Buried several inches below finished grade
B. Covered completely with mulch
C. Located at or slightly above the finished soil grade as appropriate for the site
D. Placed directly against the trunk support
Answer: Located at or slightly above the finished soil grade as appropriate for
the site
, Rationale: Planting too deeply can restrict oxygen availability, promote stem-
girdling roots, and contribute to trunk decay and long-term tree decline.
7. Which irrigation method generally provides the greatest application
efficiency for widely spaced ornamental plants?
A. Flood irrigation
B. High-pressure misting over the entire site
C. Drip or microspray irrigation targeted to the root zones
D. Uncontrolled hose flooding
Answer: Drip or microspray irrigation targeted to the root zones
Rationale: Targeted irrigation reduces unnecessary wetting of pavement,
exposed soil, and non-root areas while allowing water to be applied more
precisely.
8. A landscape drainage system repeatedly fails because runoff exceeds the
capacity of the receiving system. What is the best design response?
A. Install a smaller outlet
B. Increase pavement slope toward the building
C. Reevaluate contributing drainage area, design flow, conveyance capacity,
outlet conditions, and downstream restrictions
D. Cover the inlet with soil
Answer: Reevaluate contributing drainage area, design flow, conveyance
capacity, outlet conditions, and downstream restrictions
Rationale: Drainage systems must be evaluated as complete hydraulic systems.
Increasing only one component may simply move the problem downstream.
9. Which condition most strongly indicates that a newly installed turf area is
being irrigated excessively?
A. Slightly dry soil between irrigation cycles
B. Persistent saturation, shallow rooting, disease pressure, and runoff