MCPPO Design & Construction Contracting: Complete Exam Prep with 400+ Q&A

Document preview thumbnail
Preview 4 out of 201 pages

Prepare for the Massachusetts MCPPO Design and Construction Contracting certification with this comprehensive exam guide featuring over 400 practice questions covering all essential topics. Master public bidding laws (M.G.L. c. 149, c. 149A, c. 30 § 39M), Designer Selection Law, Owner's Project Manager requirements, alternative project delivery methods (Design-Build, CM at Risk), and the Uniform Procurement Act. Each question includes detailed rationales explaining legal requirements and practical applications. Perfect for public officials, procurement officers, project managers, and construction professionals working with Massachusetts public projects. Updated with the latest regulations and MSBA requirements, this graded A+ resource will help you achieve MCPPO certification with confidence.

Content preview

1|Page




Design and Construction Contracting (MCPPO
)Newest Exam Preparation With Complete Questions
And Correct Answers With Rationales Already
Graded A+Brand New Version!!




Question 1
Which Massachusetts statute is the primary bid law for public building
construction contracts exceeding $150,000?
A) M.G.L. c. 30, § 39M
B) M.G.L. c. 149A
C) M.G.L. c. 149
D) M.G.L. c. 7C, §§ 44-58


Answer: C
Explanation: M.G.L. c. 149 governs the competitive bidding process for
public building projects above the $150,000 threshold.


Question 2
Under M.G.L. c. 30, § 39M, which type of projects are regulated?

,2|Page


A) Public building construction
B) Public works and horizontal projects
C) Design-Build contracts only
D) Emergency procurements


Answer: B
Explanation: Section 39M applies to public works that are not building
construction, such as roads, bridges, and other horizontal infrastructure.


Question 3
What is the purpose of M.G.L. c. 7C, §§ 44-58?
A) To set wage rates for construction labor
B) To establish the Designer Selection Law (DSL)
C) To define the Uniform Procurement Act
D) To regulate demolition contracts


Answer: B
Explanation: These sections create the Designer Selection Law, which
governs how architects and engineers are chosen for public projects.


Question 4
Which delivery method allows the owner to contract with a single
entity that provides both design and construction services?

,3|Page


A) Design-Bid-Build
B) Construction Management at Risk
C) Design-Build
D) Traditional procurement


Answer: C
Explanation: Design-Build consolidates design and construction under
one contract, streamlining communication and responsibility.


Question 5
In Construction Management at Risk (CM at Risk), when does the
construction manager assume the risk of cost overruns?
A) After the design is complete and a GMP is issued
B) During the pre-design phase
C) Only if the owner changes the scope
D) Never; the risk remains with the owner


Answer: A
Explanation: The CM at Risk issues a Guaranteed Maximum Price (GMP)
after the design, assuming cost overrun risk beyond that amount.


Question 6

, 4|Page


At what project cost threshold is the hiring of an Owner's Project
Manager (OPM) mandatory?
A) $500,000
B) $1,000,000
C) $1,500,000
D) $2,000,000


Answer: C
Explanation: Massachusetts law requires an OPM for public
construction projects whose total cost equals or exceeds $1.5 million.


Question 7
What is the maximum retainage percentage permitted under
Massachusetts law for each progress payment?
A) 3%
B) 5%
C) 10%
D) 15%


Answer: B
Explanation: Massachusetts law caps retainage at a maximum of 5% of
each progress payment.

Document information

Uploaded on
August 16, 2026
Number of pages
201
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$25.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
2
Followers
2
Items
1446
Last sold
1 month ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions