Although third level players do not have direct links to the primary players, they still exercise a great deal of influence on a construction project. - Answer True Historically, the construction industry has been looked on as incredibly efficient, safe and time saving. - Answer False What is the contractor responsible for providing? - Answer Labor, material, equipment, and expertise Subcontractors typically contract directly with the owner for special or trade specific work - Answer False In environmental Construction a contractor will probably be collaborating with ecologists, chemists, biologists, and other scientists - Answer True Who is the player in charge of the project from beginning to end? - Answer Project Manager Through their use of stone and stonemasons, the Greeks pioneered the development of Arches and Domes - Answer False Which of the following are considered third level Players? - Answer Trade Associations, Local, State and Federal Gov. The industrial revolution better defined the roles of various professions involved in construction wherein contractors took on greater responsibility for technical coordination - Answer False With what is the financial officer primarily concerned - Answer the creation of the budget The owner on a construction project is accountable for which of the following - Answer Developing the program to outline the needs of the end users Second level players in the construction industry exercise great influence on a project through direct contracts with the owner, designer and contractor - Answer False

Content preview

Construction Management Final Review
Questions and Answers.
Although third level players do not have direct links to the primary players, they still exercise a
great deal of influence on a construction project. - Answer True



Historically, the construction industry has been looked on as incredibly efficient, safe and time
saving. - Answer False



What is the contractor responsible for providing? - Answer Labor, material, equipment, and
expertise



Subcontractors typically contract directly with the owner for special or trade specific work -
Answer False



In environmental Construction a contractor will probably be collaborating with ecologists,
chemists, biologists, and other scientists - Answer True



Who is the player in charge of the project from beginning to end? - Answer Project Manager



Through their use of stone and stonemasons, the Greeks pioneered the development of Arches
and Domes - Answer False



Which of the following are considered third level Players? - Answer Trade Associations, Local,
State and Federal Gov.



The industrial revolution better defined the roles of various professions involved in construction
wherein contractors took on greater responsibility for technical coordination - Answer False



With what is the financial officer primarily concerned - Answer the creation of the budget



The owner on a construction project is accountable for which of the following - Answer
Developing the program to outline the needs of the end users



Second level players in the construction industry exercise great influence on a project through
direct contracts with the owner, designer and contractor - Answer False

, The prime contractor on a construction project is the contractor that has a contract directly with
the owner - Answer True



Maintaining a relationship with upper management is one of the attributes of leadership
abilities - Answer Yes



Which of the following are Three Levels of skill developed in the middle ages - Answer
Apprentice, Journeyman, Master



There are primarily three types of architects designers, project architects, and specification
writers - Answer True



In construction a finite time frame associated with a completion date is one of the prime
characteristics of a project. - Answer True



In Construction a program is a set of instruction telling the contractor how to build the building -
Answer False



What is used to monitor the quality of a project - Answer Specifications and Drawings



What is used to monitor the scope of a project - Answer The Project program



What is not considered a construction management function - Answer Funding the Project



What is used to monitor the cost of the project - Answer The Estimate



What is used to monitor the safety of a project - Answer Potential Risk Indemnification



When an owner contracts with a architect to design a project and then places the contract out
for contractors to bid on. This is the Design-Build delivery system - Answer False



What is not a construction management job description - Answer Electrical Subcontractor



What is used to monitor the Time of the project - Answer The schedule



Construction management at risk requires the construction manager to make design inputs as
well as construct the project as a general contractor - Answer True

Document information

Uploaded on
August 16, 2026
Number of pages
12
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$13.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
COCOSOLUTIONS
4.2
(37)
Sold
220
Followers
16
Items
9281
Last sold
3 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions