EXCAVATION SAFETY BOARD EVALUATION GUARANTEED PASS UPDATED ACTUAL EXAM
QUESTIONS CORRECT ANSWERS GRADED A PLUS
Question:
Excavation Safety.
Answer:
comprises a standardized set of safety precautions that should be followed by all excavation
activities.
Question:
Excavation Safety.
Answer:
It is designed to manage risks and eliminate hazards during excavation in accordance with
regulations such as Occupational Safety and Health Standards under Rule 1410 Construction Safety.
Question:
Occupational Safety and Health Standards under Rule 1410 Construction Safety.
Answer:
Excavation is designed to manage risks and eliminate hazards during excavation in accordance with
regulations such as ________.
Question:
1413.
Answer:
Specifically, Rule _____ is for Excavation.
, Question:
Safety.
Answer:
____ must always be the priority in excavation work.
Question:
1. Open Excavation 2. Trenching 3. Dredging 4. Basement 5. Cut and Fill 6. Topsoil 7. Rock 8.
Muck 9. Earth.
Answer:
types of Excavation
Question:
Open Excavation.
Answer:
An excavation in an open ground can vary in shape and size. It is usually widerand is intended for
basement floors of buildings.
Question:
Trenching.
Answer:
It is a long and narrow excavation where the depth is greater than its width.
Question:
15 feet.
Answer:
The width at the bottom of trenching must not exceed ______.
QUESTIONS CORRECT ANSWERS GRADED A PLUS
Question:
Excavation Safety.
Answer:
comprises a standardized set of safety precautions that should be followed by all excavation
activities.
Question:
Excavation Safety.
Answer:
It is designed to manage risks and eliminate hazards during excavation in accordance with
regulations such as Occupational Safety and Health Standards under Rule 1410 Construction Safety.
Question:
Occupational Safety and Health Standards under Rule 1410 Construction Safety.
Answer:
Excavation is designed to manage risks and eliminate hazards during excavation in accordance with
regulations such as ________.
Question:
1413.
Answer:
Specifically, Rule _____ is for Excavation.
, Question:
Safety.
Answer:
____ must always be the priority in excavation work.
Question:
1. Open Excavation 2. Trenching 3. Dredging 4. Basement 5. Cut and Fill 6. Topsoil 7. Rock 8.
Muck 9. Earth.
Answer:
types of Excavation
Question:
Open Excavation.
Answer:
An excavation in an open ground can vary in shape and size. It is usually widerand is intended for
basement floors of buildings.
Question:
Trenching.
Answer:
It is a long and narrow excavation where the depth is greater than its width.
Question:
15 feet.
Answer:
The width at the bottom of trenching must not exceed ______.