1. A concrete cylinder is tested at 28 days and fails below the specified
compressive strength. Before concluding that the concrete is deficient,
what should the testing technician verify first?
A. The color of the concrete surface
B. The cylinder's identification, curing history, dimensions, and testing procedure
C. The brand of cement used
D. The ambient temperature on the day of placement
Answer: B. The cylinder's identification, curing history, dimensions, and testing
procedure
Rationale: Proper specimen identification, curing, dimensions, and test
execution must be verified before attributing a low result to deficient concrete.
Testing errors can produce an apparently low strength result.
2. During aggregate sampling from a stockpile, why should a technician avoid
taking only material from the outside surface?
,A. Surface material is always contaminated with cement
B. The surface may not represent the gradation of the entire stockpile
C. Surface material is always saturated
D. The material will contain excessive Portland cement
Answer: B. The surface may not represent the gradation of the entire stockpile
Rationale: Segregation can cause coarse particles to concentrate in some areas
and fines in others. Representative sampling is essential for valid laboratory
results.
3. A sieve analysis shows that a significant quantity of aggregate remains on
the largest sieve. What is the most appropriate action?
A. Ignore the retained material
B. Report only the material passing the largest sieve
C. Include the retained material in the total mass and evaluate whether the sieve
stack is appropriate
D. Wash the material through the sieve by force
Answer: C. Include the retained material in the total mass and evaluate whether
the sieve stack is appropriate
Rationale: All particles must be accounted for. Excessive oversize material may
also indicate that the selected sieve arrangement or sample reduction was
inappropriate.
4. What is the primary purpose of determining aggregate moisture content
before batching concrete?
A. To determine cement fineness
B. To correct the amount of mixing water contributed by the aggregate
C. To determine air content
D. To calculate concrete temperature
Answer: B. To correct the amount of mixing water contributed by the aggregate
,Rationale: Aggregate surface moisture contributes water to the concrete
mixture, while absorption affects the aggregate's internal moisture condition.
Accurate moisture corrections help maintain the designed water-cementitious
materials ratio.
5. A concrete technician measures slump immediately after obtaining a
representative sample. The slump is substantially below the project
requirement. What should the technician do first?
A. Add water without authorization
B. Record the result and follow the project's approved adjustment and retesting
procedure
C. Add cement to the sample
D. Discard the sample without documentation
Answer: B. Record the result and follow the project's approved adjustment and
retesting procedure
Rationale: Unauthorized water addition can change the designed mixture. Any
adjustment must comply with the approved mix design and project procedures.
6. Why is concrete consolidation important when preparing molded test
cylinders?
A. It increases the cement content
B. It removes entrapped air and produces a more representative specimen
C. It chemically hardens the cement
D. It eliminates the need for curing
Answer: B. It removes entrapped air and produces a more representative
specimen
Rationale: Improper consolidation can leave excessive voids and reduce
measured compressive strength, making the specimen unrepresentative of
properly placed concrete.
, 7. What does the water-cementitious materials ratio primarily influence in
hardened concrete?
A. Aggregate particle shape
B. Strength and durability characteristics
C. Reinforcing-bar diameter
D. Sieve opening size
Answer: B. Strength and durability characteristics
Rationale: Lower water-to-cementitious-materials ratios generally increase
potential strength and reduce permeability when the concrete is properly
proportioned, placed, and cured.
8. A concrete batch contains aggregate that is wetter than assumed in the
mixture design. If no correction is made, what is the likely effect?
A. The effective water content increases
B. The cement content automatically increases
C. The aggregate gradation changes to zero
D. The concrete becomes completely air-free
Answer: A. The effective water content increases
Rationale: Free moisture on aggregate particles enters the concrete mixture and
increases effective mixing water unless the batch water is adjusted.
9. What is the purpose of a concrete air-content test?
A. To measure cement fineness
B. To determine the amount of entrained and entrapped air in fresh concrete
C. To determine aggregate absorption
D. To measure reinforcement cover
Answer: B. To determine the amount of entrained and entrapped air in fresh