1. What is the minimum lot size for a single-family dwelling using
a standard OSSF without a public water supply?
A. 0.25 acres
B. 1 acre
C. 1.5 acres
D. 2 acres
A minimum of 1 acre is required when a public water supply is not
available to reduce the risk of groundwater contamination.
2. What should be done before starting the installation of a
permitted OSSF?
A. Order parts
B. Notify permitting authority for pre-cover inspection
C. Fill tank with water
D. Remove all vegetation
3. A pre-cover inspection ensures the system meets design and
regulatory requirements before backfilling.
4. A standard home with 4 bedrooms would typically require a
septic tank capacity of at least:
,
,
,