●● Which of the following is NOT an activity performed during
identifying project products and activities?
a. Identifying project team products
b. Identifying and describing project products
c. Produce ideal activity network
d. Document generic product flow
Answer: b. Identifying and describing project products
●● Which network diagramming technique uses boxes to represent
activities?
a. ADM
b. CPM
c. PDM
d. PERT
Answer: c. PDM
,●● _____ are predefined actions that the project team will take if an
identified risk event occurs.
a. Management reserves
b. Workarounds
c. Secondary risks
d. Contingency plans
Answer: d. Contingency plans
●● Which document recognizes the existence of a project and provides
direction on the project's objectives and management?
a. stakeholder register
b. directive
c. project charter
d. risk register
Answer: c. project charter
●● Which approach for constructing a WBS involves refining the work
into greater and greater levels of detail?
a. Top-down
b. analogy
,c. mind mapping
d. bottom-up
Answer: a. Top-down
●● Which characteristic of organizational culture describes the degree to
which management's decisions take into account the effect of outcomes
on people within the organization?
a. Member identity
b. Group emphasis
c. People focus
d. Unit integration
Answer: c. People focus
●● Which statement is true of tangible costs?
a. They are difficult to quantify
b. They cannot be calculated in monetary terms
c. They can be easily measured
d. Their examples include goodwill and prestige
Answer: c. They can be easily measured
●● Which dependencies do AOA network diagrams use?
, a. start-to-start
b. finish-to-start
c. start-to-finish
d. finish-to-finish
Answer: b. finish-to-start
●● The stakeholder register is the output of the _____ stakeholders
process of project stakeholder management.
a. planning
b. identifying
c. monitoring
d. executing
Answer: b. identifying
●● Development of software in-house usually means that ______.
a. the application will slot into a portfolio of existing computer systems
b. development is seen from the users viewpoint
c. development is seen from both users and developers viewpoint
d. development is seen from the developers viewpoint
AND CORRECT ANSWERS
COMPREHENSIVE STUDY GUIDE
●● Which of the following is NOT an activity performed during
identifying project products and activities?
a. Identifying project team products
b. Identifying and describing project products
c. Produce ideal activity network
d. Document generic product flow
Answer: b. Identifying and describing project products
●● Which network diagramming technique uses boxes to represent
activities?
a. ADM
b. CPM
c. PDM
d. PERT
Answer: c. PDM
,●● _____ are predefined actions that the project team will take if an
identified risk event occurs.
a. Management reserves
b. Workarounds
c. Secondary risks
d. Contingency plans
Answer: d. Contingency plans
●● Which document recognizes the existence of a project and provides
direction on the project's objectives and management?
a. stakeholder register
b. directive
c. project charter
d. risk register
Answer: c. project charter
●● Which approach for constructing a WBS involves refining the work
into greater and greater levels of detail?
a. Top-down
b. analogy
,c. mind mapping
d. bottom-up
Answer: a. Top-down
●● Which characteristic of organizational culture describes the degree to
which management's decisions take into account the effect of outcomes
on people within the organization?
a. Member identity
b. Group emphasis
c. People focus
d. Unit integration
Answer: c. People focus
●● Which statement is true of tangible costs?
a. They are difficult to quantify
b. They cannot be calculated in monetary terms
c. They can be easily measured
d. Their examples include goodwill and prestige
Answer: c. They can be easily measured
●● Which dependencies do AOA network diagrams use?
, a. start-to-start
b. finish-to-start
c. start-to-finish
d. finish-to-finish
Answer: b. finish-to-start
●● The stakeholder register is the output of the _____ stakeholders
process of project stakeholder management.
a. planning
b. identifying
c. monitoring
d. executing
Answer: b. identifying
●● Development of software in-house usually means that ______.
a. the application will slot into a portfolio of existing computer systems
b. development is seen from the users viewpoint
c. development is seen from both users and developers viewpoint
d. development is seen from the developers viewpoint