1.
Who is generally responsible for engaging the approved agency to perform
required special inspections and tests?
A. The general contractor
B. The building official
C. The owner or owner's authorized agent
D. The material supplier
Answer: The owner or owner's authorized agent
Rationale: The special-inspection system is intended to provide independent
verification of specified construction activities. The owner or owner's authorized
agent is generally responsible for employing the approved agency, subject to
applicable Georgia amendments and exceptions.
2.
,Special inspections required by Chapter 17 are best described as inspections that:
A. Replace all inspections performed by the building official
B. Supplement the inspections performed by the building official
C. Are performed only after occupancy
D. Are optional unless requested by the contractor
Answer: Supplement the inspections performed by the building official
Rationale: Special inspections are additional inspections intended to verify
particular materials, systems, or construction activities that require specialized
expertise or enhanced quality control.
3.
Before construction begins, an approved agency should provide the building
official with documentation demonstrating:
A. The contractor's profit margin
B. The special inspector's competence and relevant experience or training
C. The project's final cost
D. The manufacturer's warranty
Answer: The special inspector's competence and relevant experience or training
Rationale: Qualification documentation establishes that personnel assigned to
special inspections possess appropriate competence for the complexity and
materials involved.
4.
Which document identifies the inspections and tests required for a particular
project?
A. Certificate of occupancy
B. Statement of special inspections
C. Contractor's daily log
D. Certificate of substantial completion
,Answer: Statement of special inspections
Rationale: The statement of special inspections identifies the required special
inspections and tests and establishes the inspection framework for the project.
5.
A special inspector discovers reinforcing steel that does not conform to the
approved structural drawings. What should the inspector do first?
A. Authorize the contractor to conceal the steel
B. Ignore the discrepancy if the concrete strength is adequate
C. Report the discrepancy through the required inspection-reporting process
D. Redesign the reinforcement in the field
Answer: Report the discrepancy through the required inspection-reporting
process
Rationale: A special inspector observes and documents compliance; the
inspector does not independently redesign structural work. Significant
discrepancies must be communicated to the responsible parties.
6.
Which activity is generally outside the proper role of a special inspector?
A. Observing reinforcing-bar placement
B. Documenting test results
C. Approving unauthorized structural redesigns
D. Reporting nonconforming work
Answer: Approving unauthorized structural redesigns
Rationale: The special inspector verifies construction against approved
documents and applicable requirements. Design changes must be handled by
the appropriate design professional and approved through the required process.
7.
, A special inspector should compare field conditions primarily against:
A. Verbal instructions from a laborer
B. Approved construction documents and applicable code requirements
C. The contractor's previous project
D. A manufacturer's advertisement
Answer: Approved construction documents and applicable code requirements
Rationale: Inspection decisions must be based on the governing documents,
approved plans, specifications, applicable codes, and approved modifications.
8.
If required special inspections are not performed, the primary concern is that:
A. The project may have inadequate verification of critical construction
B. The contractor will automatically lose its license
C. The building will automatically collapse
D. The permit becomes a warranty
Answer: The project may have inadequate verification of critical construction
Rationale: Special inspections provide documented verification of construction
activities that can significantly affect structural or life-safety performance.
9.
Which item is most important when establishing inspection frequency?
A. The inspector's personal preference
B. The approved statement of special inspections and applicable code
requirements
C. The contractor's payroll schedule
D. The weather forecast alone
Answer: The approved statement of special inspections and applicable code
requirements