Qualifying Examination Practice Exam
2026 | 100 Questions & Answers with
Detailed Rationales | Complete Exam
Prep & Study Guide
1. Which entity regulates residential and general contractor licensing in
Georgia?
A. Georgia Department of Labor
B. Georgia State Licensing Board for Residential and General Contractors
C. Georgia Department of Revenue
D. Georgia Secretary of State Elections Division
Answer: Georgia State Licensing Board for Residential and General Contractors
Rationale: The State Licensing Board establishes and administers licensing
requirements for residential and general contractors in Georgia.
2. What is the primary purpose of a contractor qualifying examination?
A. To determine a contractor's credit score
B. To verify technical and regulatory competency
C. To establish material prices
D. To assign construction projects
,Answer: To verify technical and regulatory competency
Rationale: Contractor examinations are designed to demonstrate that
applicants possess the knowledge necessary to perform contracting work
competently and lawfully.
3. A residential basic contractor is generally authorized to construct or
manage which type of work?
A. Only electrical installations
B. Residential structures within the scope allowed by the license
C. Only plumbing systems
D. Only commercial high-rise buildings
Answer: Residential structures within the scope allowed by the license
Rationale: A Residential Basic Contractor license covers qualifying residential
construction activities within the statutory and licensing scope.
4. Which document normally provides the detailed requirements for a
construction project?
A. Building permit receipt
B. Construction plans and specifications
C. Contractor business card
D. Material delivery ticket
Answer: Construction plans and specifications
Rationale: Plans and specifications communicate the design, dimensions,
materials, workmanship, and other requirements for the project.
5. What is the primary purpose of a building permit?
A. To guarantee profitability
B. To authorize regulated construction work and facilitate code enforcement
C. To establish the contractor's insurance rate
D. To replace construction drawings
,Answer: To authorize regulated construction work and facilitate code
enforcement
Rationale: Permits allow the applicable authority to review and inspect
construction for compliance with adopted requirements.
6. Who is generally responsible for ensuring that required permits are
obtained before beginning regulated work?
A. The material supplier only
B. The contractor/property owner as required by applicable law
C. The building inspector only
D. The equipment rental company
Answer: The contractor/property owner as required by applicable law
Rationale: Permit responsibility depends on the applicable jurisdiction and
project arrangement, but required permits must be secured before regulated
work proceeds.
7. What does the term "means and methods" generally refer to?
A. The owner's financing arrangements
B. How construction work is performed
C. The architect's professional license
D. The project's property taxes
Answer: How construction work is performed
Rationale: Means and methods include procedures, techniques, sequences, and
equipment used to accomplish construction work.
8. What is a change order?
A. A replacement building permit
B. A written modification to the contract work, price, or time
C. A supplier invoice
D. A certificate of occupancy
, Answer: A written modification to the contract work, price, or time
Rationale: Change orders document agreed modifications to the original
contract requirements.
9. Why should change orders be documented in writing?
A. To eliminate all taxes
B. To establish a clear record of the parties' agreement
C. To avoid inspections
D. To eliminate the need for plans
Answer: To establish a clear record of the parties' agreement
Rationale: Written change orders reduce disputes by identifying what changed
and how the change affects cost and schedule.
10.What is the purpose of a construction schedule?
A. To identify planned activities and their timing
B. To determine property ownership
C. To replace the contract
D. To calculate sales tax only
Answer: To identify planned activities and their timing
Rationale: A schedule helps coordinate labor, materials, inspections,
subcontractors, and project completion.
11.What is critical path analysis used for?
A. Determining property boundaries
B. Identifying activities that control project duration
C. Calculating concrete strength
D. Selecting insurance carriers
Answer: Identifying activities that control project duration