1. What is the primary objective of data center design?
A. Maximize office space
B. Provide reliable, secure, efficient infrastructure for ICT
operations
C. Minimize the number of IT devices
D. Eliminate all maintenance requirements
Answer: B. Provide reliable, secure, efficient infrastructure for
ICT operations
Rationale: Data center design integrates electrical, mechanical,
architectural, ICT, security, fire protection, and operational
requirements to support critical IT services.
2. Which activity should generally occur early in the data
center design process?
A. Selecting furniture
B. Identifying project requirements
C. Painting the equipment room
D. Installing servers
,Answer: B. Identifying project requirements
Rationale: Requirements establish capacity, availability,
security, environmental, operational, and growth objectives
that guide the design.
3. Which factor is most important when evaluating a potential
data center site?
A. Interior decoration
B. Availability of reliable utilities
C. Number of nearby restaurants
D. Office carpet color
Answer: B. Availability of reliable utilities
Rationale: Reliable electrical power, telecommunications
connectivity, water where required, and other utilities are
fundamental to data center operation.
4. Why is future growth considered during data center
planning?
A. To increase unnecessary construction
B. To allow capacity expansion without major disruption
C. To eliminate commissioning
D. To reduce security requirements
Answer: B. To allow capacity expansion without major
disruption
,Rationale: Data centers often have long service lives, so
scalable infrastructure can accommodate changing IT loads.
5. Which discipline is normally involved in determining
structural loading requirements?
A. Structural engineering
B. Graphic design
C. Marketing
D. Human resources
Answer: A. Structural engineering
Rationale: Structural engineers evaluate floor loading,
equipment loads, seismic considerations, roof loads, and other
structural requirements.
6. What does redundancy primarily provide in a critical
facility?
A. Decorative flexibility
B. Continued operation when a component fails or is
unavailable
C. Lower security
D. Reduced documentation
Answer: B. Continued operation when a component fails or is
unavailable
, Rationale: Redundancy provides alternate capacity or pathways
so that failure or maintenance of one component does not
necessarily interrupt critical operations.
7. What is the purpose of a data center capacity plan?
A. Determine employee salaries
B. Forecast and manage required infrastructure resources
C. Select office furniture
D. Replace security policies
Answer: B. Forecast and manage required infrastructure
resources
Rationale: Capacity planning addresses power, cooling, space,
connectivity, and other resources needed now and in the
future.
8. Which is an example of a critical data center infrastructure
system?
A. Electrical distribution
B. Cafeteria equipment
C. Office printer
D. Reception desk
Answer: A. Electrical distribution
Rationale: Electrical distribution directly supports critical IT and
facility loads.