1. What is the primary purpose of a plans examiner reviewing construction
documents?
A. To redesign the project for the owner
B. To verify that the proposed work complies with applicable codes and
regulations
C. To determine the contractor's profit
D. To approve the contractor's construction schedule
Answer: To verify that the proposed work complies with applicable codes and
regulations
Rationale: A plans examiner evaluates submitted documents for compliance
with applicable building, fire, accessibility, structural, energy, and related
requirements.
, 2. Which document normally establishes the intended use and occupancy of a
building?
A. Foundation plan
B. Door schedule
C. Code analysis
D. Finish schedule
Answer: Code analysis
Rationale: The code analysis identifies occupancy classification, construction
type, allowable area, height, occupant load, egress requirements, and other
governing code criteria.
3. What should a plans examiner do when drawings contain conflicting
dimensions?
A. Select whichever dimension appears most convenient
B. Ignore both dimensions
C. Request clarification or correction from the design professional
D. Allow the contractor to decide in the field
Answer: Request clarification or correction from the design professional
Rationale: Conflicting information must be resolved before approval so that
construction requirements are clearly established.
4. What information is especially important on a site plan?
A. Employee salaries
B. Property lines and building location
C. Contractor's tax return
D. Interior furniture colors
Answer: Property lines and building location
,Rationale: Site plans allow the reviewer to evaluate setbacks, lot coverage, fire
access, utilities, and the relationship of the building to property lines and other
structures.
5. What is the purpose of a building code analysis?
A. To calculate contractor payroll
B. To demonstrate how the project satisfies applicable code requirements
C. To select construction equipment
D. To establish the project's advertising budget
Answer: To demonstrate how the project satisfies applicable code requirements
Rationale: A properly prepared code analysis provides the examiner with the
fundamental information needed to verify compliance.
6. Occupancy classification is primarily based on what factor?
A. Exterior color
B. Building height alone
C. The use and characteristics of the space
D. Property value
Answer: The use and characteristics of the space
Rationale: Occupancy classifications are based on how spaces are used and the
hazards or occupant characteristics associated with those uses.
7. A building contains several different uses. What should the plans examiner
first determine?
A. The owner's preferred occupancy classification
B. Whether the uses are classified as accessory, incidental, or separate
occupancies under the applicable code
C. The contractor's experience
D. The number of construction workers
, Answer: Whether the uses are classified as accessory, incidental, or separate
occupancies under the applicable code
Rationale: Multiple uses can affect allowable area, separation, egress, fire
protection, and other requirements.
8. What is an occupant load?
A. The number of construction workers on the job
B. The number of occupants for whom a space is designed or calculated
C. The number of parking spaces
D. The number of exits provided
Answer: The number of occupants for whom a space is designed or calculated
Rationale: Occupant load is used to establish requirements such as egress
capacity, plumbing fixtures, and sometimes fire protection provisions.
9. Why is occupant load important during plan review?
A. It determines the building's paint colors
B. It affects means of egress and other life-safety requirements
C. It establishes contractor licensing fees
D. It determines property taxes
Answer: It affects means of egress and other life-safety requirements
Rationale: Egress capacity, number of exits, plumbing fixtures, and other
provisions can depend on occupant load.
10.What is the purpose of a construction type classification?
A. To identify the building's architectural style
B. To establish the fire-resistance and combustibility characteristics of building
elements
C. To establish the contractor's license level
D. To determine the property's assessed value