SECTION 1: MANAGING COMMISSIONING PROJECTS (Questions 1-60)
Overview
This domain covers project management responsibilities of the Commissioning Provider (CxP):
developing the commissioning team, managing the budget and scope, participating in design
and construction meetings, tracking deficiencies, facilitating risk assessment, and coordinating
the overall commissioning process.
QUESTION 1
What is the primary purpose of a commissioning process?
A) To ensure all equipment is installed correctly
, Page 2 of 122
B) To verify that building systems perform interactively according to design intent and the
owner's operational requirements
C) To reduce construction costs
D) To test all equipment before occupancy
Correct Answer: B
Rationale: The commissioning process is a quality assurance process to help ensure all building
systems perform interactively and according to the design intent and the owner's operational
requirements . It goes beyond simple equipment testing to verify integrated system
performance. The process focuses on verifying and documenting that all commissioned systems
and assemblies are planned, designed, installed, tested, operated, and maintained to meet the
Owner's Project Requirements .
QUESTION 2
Which document defines the owner's goals, expectations, and performance requirements for a
building project?
A) Basis of Design (BOD)
B) Owner's Project Requirements (OPR)
C) Commissioning Plan
D) Systems Manual
Correct Answer: B
Rationale: The Owner's Project Requirements (OPR) document defines the owner's goals,
, Page 3 of 122
expectations, and performance requirements for the building project . It serves as the
foundation for all commissioning activities. The Basis of Design (BOD) describes how the design
team intends to meet the OPR, the Commissioning Plan outlines the commissioning process,
and the Systems Manual is a final deliverable for operations.
QUESTION 3
The Basis of Design (BOD) document describes:
A) The owner's operational requirements
B) The design concepts and assumptions used to meet the OPR
C) The commissioning process
D) Training requirements
Correct Answer: B
Rationale: The Basis of Design (BOD) documents the design concepts, calculations, and
assumptions used by the design team to meet the Owner's Project Requirements . The OPR
defines the owner's operational requirements, the Commissioning Plan defines the
commissioning process, and training requirements are typically addressed in the commissioning
specifications.
QUESTION 4
Who is responsible for leading the commissioning process?
A) General Contractor
, Page 4 of 122
B) Commissioning Provider (CxP)
C) Design Engineer
D) Building Owner
Correct Answer: B
Rationale: The Commissioning Provider (CxP) is responsible for leading, planning, coordinating,
and managing the commissioning team to implement commissioning processes . The term
"Commissioning Provider" (CxP) is adopted by ASHRAE to identify those who lead the process .
QUESTION 5
Which of the following is a key deliverable of the Pre-Design phase of commissioning?
A) Functional performance test procedures
B) The Owner's Project Requirements (OPR)
C) Systems Manual
D) Training documentation
Correct Answer: B
Rationale: The Pre-Design phase includes developing the Owner's Project Requirements (OPR)
and establishing the commissioning scope and budget . Functional performance test procedures
and training documentation are developed later in the process, and the Systems Manual is a
final deliverable.