1. What is the primary purpose of a local building permit?
A. To establish the contractor's profit margin
B. To authorize construction and verify compliance with applicable codes
C. To replace the construction contract
D. To eliminate the need for inspections
Answer: B. To authorize construction and verify compliance with applicable
codes
Rationale: A building permit provides legal authorization for regulated
construction and allows the jurisdiction to verify compliance through plan
review and inspections.
2. Who generally has authority to issue a local building permit?
A. The project owner
B. The material supplier
, C. The local building department or authority having jurisdiction
D. The architect's assistant
Answer: C. The local building department or authority having jurisdiction
Rationale: The authority having jurisdiction (AHJ) administers permitting and
code enforcement within its jurisdiction.
3. A contractor begins permitted work before the required permit is issued.
What is the most appropriate concern?
A. The contractor may be performing unauthorized work
B. The contractor automatically receives a permit
C. The owner becomes the inspector
D. The plans become permanently approved
Answer: A. The contractor may be performing unauthorized work
Rationale: Required permits generally must be obtained before regulated work
begins. Starting early can result in stop-work orders, fees, or other enforcement
action.
4. What does an AHJ primarily do?
A. Set the contractor's labor rates
B. Enforce applicable construction regulations and approve regulated work
C. Supply all construction materials
D. Guarantee project profitability
Answer: B. Enforce applicable construction regulations and approve regulated
work
Rationale: The AHJ administers applicable building regulations, reviews plans,
conducts inspections, and enforces code requirements.
5. If approved construction plans conflict with field conditions, what should
the contractor generally do?
A. Ignore the plans
B. Make an undocumented change
, C. Consult the design professional and AHJ as required before proceeding
D. Allow a subcontractor to decide
Answer: C. Consult the design professional and AHJ as required before
proceeding
Rationale: Significant deviations from approved documents may require
clarification, revised drawings, or approval before construction continues.
6. Which document typically identifies the intended construction
requirements in detail?
A. Approved construction documents
B. Contractor's business card
C. Delivery ticket
D. Employee time sheet
Answer: A. Approved construction documents
Rationale: Construction documents can include drawings, specifications,
schedules, and other approved information defining the scope and
requirements.
7. What is the best reason to maintain current approved plans at the jobsite?
A. They eliminate inspections
B. They provide workers and inspectors with the approved basis of
construction
C. They replace safety procedures
D. They establish material prices
Answer: B. They provide workers and inspectors with the approved basis of
construction
Rationale: Current approved documents help ensure that construction follows
the permitted design and provide inspectors with a reference during inspections.
8. What is a change order?
A. A worker's daily attendance record
, B. A formal modification to the scope, cost, or time of a construction
contract
C. A building permit
D. An inspection sticker
Answer: B. A formal modification to the scope, cost, or time of a construction
contract
Rationale: Change orders document agreed changes to contractual work,
including potential adjustments to price and schedule.
9. Why should change orders generally be documented before performing
changed work?
A. To establish clear authorization and avoid disputes
B. To eliminate the need for permits
C. To prevent inspections
D. To increase material waste
Answer: A. To establish clear authorization and avoid disputes
Rationale: Written authorization clarifies what changed, who approved it, and
how the change affects cost and schedule.
10.What is the primary purpose of a construction inspection?
A. To determine the contractor's profit
B. To verify that regulated work complies with applicable requirements
C. To select subcontractors
D. To negotiate material prices
Answer: B. To verify that regulated work complies with applicable requirements
Rationale: Inspections provide the AHJ with an opportunity to verify compliance
at required stages of construction.
11.When should a contractor request a required inspection?
A. Only after the entire project is complete
B. When the work reaches the stage specified by the jurisdiction