CM 7207 FINAL EXAM QUESTIONS AND ANSWERS
2026
A significant difference between "planning" and "scheduling" is,
a. Scheduling determines how to do, and planning determines what to do.
b. Scheduling determines how to do, and planning determines by whom.
c. Scheduling determines what is going to be done, and planning determines how to do.
d. Scheduling determines when to do, and planning determines what to do, how to do
and by whom. - Answers - d. Scheduling determines when to do, and planning
determines what to do, how to do and by whom.
What is not true about an activity?
a. An activity usually has a start time and a finish time.
b. An activity usually takes time.
c. An activity usually does not need to be measurable.
d. An activity may consume resources. - Answers - c. An activity usually does not need
to be measurable.
There is an activity, installing exterior sheathing. A crew can install 1,200 sf per day,
and the total quantity is 3,200 SF. What is the duration of this activity?
a. 1 day
b. 3 days
c. 4 days
d. 2 days - Answers - b. 3 days
A critical activity is the one that has
a. None of the above
b. Negative Float
c. No float
d. Positive float - Answers - c. No float
What is not true about an event?
Select one or more:
a. An event has a start time and a finish time.
b. An event usually takes time.
c. An event is not an activity.
d. An event usually consumes resources. - Answers - b. An event usually takes time.
d. An event usually consumes resources.
2026
A significant difference between "planning" and "scheduling" is,
a. Scheduling determines how to do, and planning determines what to do.
b. Scheduling determines how to do, and planning determines by whom.
c. Scheduling determines what is going to be done, and planning determines how to do.
d. Scheduling determines when to do, and planning determines what to do, how to do
and by whom. - Answers - d. Scheduling determines when to do, and planning
determines what to do, how to do and by whom.
What is not true about an activity?
a. An activity usually has a start time and a finish time.
b. An activity usually takes time.
c. An activity usually does not need to be measurable.
d. An activity may consume resources. - Answers - c. An activity usually does not need
to be measurable.
There is an activity, installing exterior sheathing. A crew can install 1,200 sf per day,
and the total quantity is 3,200 SF. What is the duration of this activity?
a. 1 day
b. 3 days
c. 4 days
d. 2 days - Answers - b. 3 days
A critical activity is the one that has
a. None of the above
b. Negative Float
c. No float
d. Positive float - Answers - c. No float
What is not true about an event?
Select one or more:
a. An event has a start time and a finish time.
b. An event usually takes time.
c. An event is not an activity.
d. An event usually consumes resources. - Answers - b. An event usually takes time.