CDT FINAL PAPER EXAM QUESTIONS ACCURATE ANSWERS FULL SOLUTION
CDT Examprep 2026/2027 Questions and Answers
Verified Solutions Latest Update
Question:
Before a model building code can become the building code for a jurisdiction, it has to be adopted
by? (A) Authority Having Jurisdiction (B) State Government (C) Building Inspector (D)
International Organization for Standardization -
Answer:
A Reference: PDPG 4.3 Explanation: Before a model building code can become the building code
for a jurisdiction, it has to be adopted by that AHJ. Once adopted, they then are responsible for
enforcing that building code within their jurisdiction.
Question:
The Construction Manager is hired by this entity? (A) The General contractor (B) Owner (C) A/E
(D) Contract Administrator -
Answer:
B Reference: PDPG 2.6.4 Explanation: The owner usually engages the services of a construction
manager, an entity that typically contracts with the owner to provide construction management
services.
Question:
The parties to the Construction Agreement are? (A) General Contractor, Sub Contractor, and
Construction Manager (B) A/E, General Contractor, and Contract Administrator (C) Building
Official, and General contractor (D) Owner, Contractor, and A/E -
Answer:
D Reference: PDPG 7.2.3.1 Explanation: (PDPG Figure 5.1) The tripartite relationship among the
owner, contractor, and A/E is created by obligations to third parties to the contract. For example, the
owner-A/E agreement may require certain duties of the A/E acting on behalf of the owner during
construction. The contractor has a right to rely on the proper performance of these duties. The A/E,
similarly, relies on the contractor to perform certain duties identified in the owner-contractor
agreement, even though the A/E is not a party to that contract. The A/E relationship to the contractor
,in the owner-contractor agreement is a third-party relationship. These third-party relationships
create the third side of the triangle in the construction process.(PDPG 7.2.3.1) The owner contracts
first with the A/E to design the project and to prepare bidding documents. The owner then obtains
bids through the competitive bidding process from bidding contractors. When one of he bidders is
selected by the owner, the owner will either directly enter into the contract (such as for a project to
be constructed with public funds), or negotiate the final cost and then enter into the contract (such as
for a privately funded project).
Question:
The organization responsible for the General Conditions known as 201 are? (A) DBIA (B) AGC (C)
AIA (D) CSI -
Answer:
C Reference: PDPG 11.5.4.2 Explanation: Each document deals with project conditions and issues
in a similar manner but with language determined to be in accord with the needs of each
organization.
Question:
When there is a dispute between the specifications and the drawings, what is the proper way to settle
the dispute? (A) The drawings have priority (B) The A/E should interpret (C) The specifications (D)
Arbitration -
Answer:
B Reference: PDPG 11.2.9.4, 13.9.1.1, AIA A201 1.2.1 Explanation: The drawings and
specification are complementary documents in the AIA and EJCDC general conditions. (PDPG
11.2.9.4) Precedence: Questions of precedence often arise among large scale drawings, small-scale
drawings, and specifications. However, the use of statements in the project manual to establish the
precedence of the various contract documents is not recommended because the documents are
complementary. The general conditions of the contract should indicate only that in a case of conflict
between drawings and specifications, the A/E will make a documented interpretation. (PDPG
13.9.1.1) When the contract documents are being interpreted, the contents of the drawings and the
specifications must be considered together. If an item is not addressed in both the drawings and the
specifications, it does not mean that it is not required for the project. (AIA A201 1.2.1) The Contract
Documents are complementary, and what is required by one shall be as binding as if required by all
Question:
, A subcontractor is obligated to the prime contractor in the same manner as the prime contractor is
obligated to the: (A) Architect (B) Owner (C) Material Supplier (D) Principal in Charge -
Answer:
B Reference: PDPG 2.4.2, 2.5 Explanation: A subcontractor generally provides labor at the site. A
material supplier furnishes the materials for others to install. (PDPG 2.4.2)Subcontractor: An entity
that has a direct contract with the contractor to perform a portion of the work of the project at the
site. (PDPG 2.5) Supplier: Furnishes or supplies products or services for the project, but does not
perform labor at the site.
Question:
The requirements of the general conditions can be modified or expanded to accommodate specific
project conditions, owner's requirements, or unusual aspects relating to the roles, rights, duties, and
responsibilities of the parties to the contract for construction, in this document: (A) Contract
Modifications (B) Supplemental Conditions (C) Addendum (D) Consensus Documents -
Answer:
B Reference: PDPG 11.5.4.3 Explanation: The requirements of the general conditions can be
modified or expanded in the supplementary conditions to accommodate specific project conditions,
owner's requirements, or unusual aspects relating to the roles, rights, duties, and responsibilities of
the parties to the contract for construction. Supplementary conditions are not standard for every
project and must be prepared based on requirements of the specific project.
Question:
Which of the following are not legal binding construction documents? (A) General Conditions (B)
Specifications (C) Preliminary Project Description (D) Addendum -
Answer:
C Reference: PDPG 9.3.2 Explanation: Preliminary project descriptions are associated with the
Schematic Design Phase and are informational documents that are not used for construction.
Question:
This document states that the contractor shall review, approve, and submit to the architect, shop
drawings, product data, samples, and similar submittals required by the contract documents. It also
states that the architect will review and approve or take other appropriate action upon the
contractor's submittals: (A) Construction Agreement (B) Field Order (C) General Requirements (D)
CDT Examprep 2026/2027 Questions and Answers
Verified Solutions Latest Update
Question:
Before a model building code can become the building code for a jurisdiction, it has to be adopted
by? (A) Authority Having Jurisdiction (B) State Government (C) Building Inspector (D)
International Organization for Standardization -
Answer:
A Reference: PDPG 4.3 Explanation: Before a model building code can become the building code
for a jurisdiction, it has to be adopted by that AHJ. Once adopted, they then are responsible for
enforcing that building code within their jurisdiction.
Question:
The Construction Manager is hired by this entity? (A) The General contractor (B) Owner (C) A/E
(D) Contract Administrator -
Answer:
B Reference: PDPG 2.6.4 Explanation: The owner usually engages the services of a construction
manager, an entity that typically contracts with the owner to provide construction management
services.
Question:
The parties to the Construction Agreement are? (A) General Contractor, Sub Contractor, and
Construction Manager (B) A/E, General Contractor, and Contract Administrator (C) Building
Official, and General contractor (D) Owner, Contractor, and A/E -
Answer:
D Reference: PDPG 7.2.3.1 Explanation: (PDPG Figure 5.1) The tripartite relationship among the
owner, contractor, and A/E is created by obligations to third parties to the contract. For example, the
owner-A/E agreement may require certain duties of the A/E acting on behalf of the owner during
construction. The contractor has a right to rely on the proper performance of these duties. The A/E,
similarly, relies on the contractor to perform certain duties identified in the owner-contractor
agreement, even though the A/E is not a party to that contract. The A/E relationship to the contractor
,in the owner-contractor agreement is a third-party relationship. These third-party relationships
create the third side of the triangle in the construction process.(PDPG 7.2.3.1) The owner contracts
first with the A/E to design the project and to prepare bidding documents. The owner then obtains
bids through the competitive bidding process from bidding contractors. When one of he bidders is
selected by the owner, the owner will either directly enter into the contract (such as for a project to
be constructed with public funds), or negotiate the final cost and then enter into the contract (such as
for a privately funded project).
Question:
The organization responsible for the General Conditions known as 201 are? (A) DBIA (B) AGC (C)
AIA (D) CSI -
Answer:
C Reference: PDPG 11.5.4.2 Explanation: Each document deals with project conditions and issues
in a similar manner but with language determined to be in accord with the needs of each
organization.
Question:
When there is a dispute between the specifications and the drawings, what is the proper way to settle
the dispute? (A) The drawings have priority (B) The A/E should interpret (C) The specifications (D)
Arbitration -
Answer:
B Reference: PDPG 11.2.9.4, 13.9.1.1, AIA A201 1.2.1 Explanation: The drawings and
specification are complementary documents in the AIA and EJCDC general conditions. (PDPG
11.2.9.4) Precedence: Questions of precedence often arise among large scale drawings, small-scale
drawings, and specifications. However, the use of statements in the project manual to establish the
precedence of the various contract documents is not recommended because the documents are
complementary. The general conditions of the contract should indicate only that in a case of conflict
between drawings and specifications, the A/E will make a documented interpretation. (PDPG
13.9.1.1) When the contract documents are being interpreted, the contents of the drawings and the
specifications must be considered together. If an item is not addressed in both the drawings and the
specifications, it does not mean that it is not required for the project. (AIA A201 1.2.1) The Contract
Documents are complementary, and what is required by one shall be as binding as if required by all
Question:
, A subcontractor is obligated to the prime contractor in the same manner as the prime contractor is
obligated to the: (A) Architect (B) Owner (C) Material Supplier (D) Principal in Charge -
Answer:
B Reference: PDPG 2.4.2, 2.5 Explanation: A subcontractor generally provides labor at the site. A
material supplier furnishes the materials for others to install. (PDPG 2.4.2)Subcontractor: An entity
that has a direct contract with the contractor to perform a portion of the work of the project at the
site. (PDPG 2.5) Supplier: Furnishes or supplies products or services for the project, but does not
perform labor at the site.
Question:
The requirements of the general conditions can be modified or expanded to accommodate specific
project conditions, owner's requirements, or unusual aspects relating to the roles, rights, duties, and
responsibilities of the parties to the contract for construction, in this document: (A) Contract
Modifications (B) Supplemental Conditions (C) Addendum (D) Consensus Documents -
Answer:
B Reference: PDPG 11.5.4.3 Explanation: The requirements of the general conditions can be
modified or expanded in the supplementary conditions to accommodate specific project conditions,
owner's requirements, or unusual aspects relating to the roles, rights, duties, and responsibilities of
the parties to the contract for construction. Supplementary conditions are not standard for every
project and must be prepared based on requirements of the specific project.
Question:
Which of the following are not legal binding construction documents? (A) General Conditions (B)
Specifications (C) Preliminary Project Description (D) Addendum -
Answer:
C Reference: PDPG 9.3.2 Explanation: Preliminary project descriptions are associated with the
Schematic Design Phase and are informational documents that are not used for construction.
Question:
This document states that the contractor shall review, approve, and submit to the architect, shop
drawings, product data, samples, and similar submittals required by the contract documents. It also
states that the architect will review and approve or take other appropriate action upon the
contractor's submittals: (A) Construction Agreement (B) Field Order (C) General Requirements (D)