ACG GUIDELINE EXAM WITH CORRECT
ACTUAL QUESTIONS AND CORRECTLY WELL
DEFINED ANSWERS LATEST ALREADY GRADED
A
Terms in this set (110)
What are the five phases of 1.) Pre-Design
commissioning? 2.) Design
3.) Construction
4.) Acceptance
5.) Post-Acceptance
Studies indicate _ to _% savings in 8 to 20%
building operating costs when
comparing a comissioned building
to a non-commissioned building.
What is commissioning? A process of documentation, adjustment, testing,
verification, and training performed specifically
to ensure that the finished facility operates in
accordance with the owner's documented
project requirements and the construction
documents. Commissioning serves the owner's
best interests by delivering a facility with systems
that perform as specified, intended, and paid for.
,What does DID mean and provide a Design Intent Document - Details functional
brief definition? requirements and Owner's expectations of how a
building will be used and operated - Owner's
Project Requirements
What does BOD mean and provide Basis of Design - The concepts, calculations,
a brief definition? decisions, and product selections used to meet
the Owner's Project Requirements.
Designer's (A/E) services typically Do NOT
(do or do not) include field
verification that their design works
as intended.
Construction Manager's services Do NOT
typically (do or do not) include
functional verification that the
installed systems meet design
intent.
The CxA has a distinct responsibility The Owner
to who?
The CxA is not just another layer of Communication that makes quality solutions
inspection, but a catalyst for? possible.
The CxA (is or is not) an inspector. Is NOT
, The commissioning process Owner's Project Requirements; Design and
provides verification that the ____ ____ Construction
____ are implemented in both the ____
and ____.
New construction commissioning 0.5 to 1.5%
costs _ to _% of total construction
cost.
Retrocommissioning costs _ to _% of 3 to 5%
total operation cost.
New construction commissioning 2 to 3%
costs _ to _% of total mechanical
system construction cost.
New construction commissioning 1 to 2%
costs _ to _% of total electrical
system construction cost.
New construction commissioning 2 to 5%
costs _ to _% of total comprehensive
HVAC construction cost.
ACTUAL QUESTIONS AND CORRECTLY WELL
DEFINED ANSWERS LATEST ALREADY GRADED
A
Terms in this set (110)
What are the five phases of 1.) Pre-Design
commissioning? 2.) Design
3.) Construction
4.) Acceptance
5.) Post-Acceptance
Studies indicate _ to _% savings in 8 to 20%
building operating costs when
comparing a comissioned building
to a non-commissioned building.
What is commissioning? A process of documentation, adjustment, testing,
verification, and training performed specifically
to ensure that the finished facility operates in
accordance with the owner's documented
project requirements and the construction
documents. Commissioning serves the owner's
best interests by delivering a facility with systems
that perform as specified, intended, and paid for.
,What does DID mean and provide a Design Intent Document - Details functional
brief definition? requirements and Owner's expectations of how a
building will be used and operated - Owner's
Project Requirements
What does BOD mean and provide Basis of Design - The concepts, calculations,
a brief definition? decisions, and product selections used to meet
the Owner's Project Requirements.
Designer's (A/E) services typically Do NOT
(do or do not) include field
verification that their design works
as intended.
Construction Manager's services Do NOT
typically (do or do not) include
functional verification that the
installed systems meet design
intent.
The CxA has a distinct responsibility The Owner
to who?
The CxA is not just another layer of Communication that makes quality solutions
inspection, but a catalyst for? possible.
The CxA (is or is not) an inspector. Is NOT
, The commissioning process Owner's Project Requirements; Design and
provides verification that the ____ ____ Construction
____ are implemented in both the ____
and ____.
New construction commissioning 0.5 to 1.5%
costs _ to _% of total construction
cost.
Retrocommissioning costs _ to _% of 3 to 5%
total operation cost.
New construction commissioning 2 to 3%
costs _ to _% of total mechanical
system construction cost.
New construction commissioning 1 to 2%
costs _ to _% of total electrical
system construction cost.
New construction commissioning 2 to 5%
costs _ to _% of total comprehensive
HVAC construction cost.