OPMA 317 - MIDTERM EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 ABC classification - Answers application of Pareto analysis that divides on-hand inventory into 3 classifications based on annual dollar volume or usage Activity - Answers a task that consumes time and resources Additional crashing exercise - Answers pg. 75 of management and scheduling ppt Additional factors for project success - Answers long-term view would include corporate social responsibility and environmental performance Addressing variability in take time in line balancing - Answers add an inventory before an inconsistent station for a buffer in variability Adjusting demand with revenue/yield management - Answers adjusting demand patterns using price structures to flatten demand curves while maintaining service level Assemble-to-order - Answers half outsourcing to standardize production and half customer specific production, includes "postponement" Assembly line balancing steps - Answers 1. Draw a precedence diagram including task times 2. determine required cycle time (C) to meet demand 3. determine total work time per unit (T) 4. determine number of work stations needed (N) 5. Assign tasks to stations using trial and error approach 6. Evaluate efficiency of process 7. redesign the line if not satisfactory Assembly line balancing steps (3) - Answers draw the precedence diagram, determine the required cycle time (to complete X in y time we have to finish one x in z minutes), assign tasks to stations Assembly line example - Answers capacity management ppt, slide 27 Average on hand quantity - Answers average of the saw tooth pattern for inventory, ends up being (Q/2) Backflushing - Answers record that product was completed in software which then reduces all required components for tracking purposes Base SD % coverage - Answers 1SD 68.2%, 2SD 95.4%, 3SD 99.7% Benefits for ABC classification (4) - Answers purchasing and supplier development, demand forecasting, physical inventory control, and inventory counting (check A frequently and C's rarely) Bottleneck - Answers the slowest part of the a process that constrains capacity Bottleneck processing time - Answers is equal to the the cycle time for the entire process Calculating path completion probabilities - Answers to determine if a path can be completed by a certain date consult the z score Calculating project duration for a confidence level - Answers solve for D in the z-score formula to determine number of days to produce a certain duration with a certain confidence Capacity - Answers the maximum production output possible in a time period Capacity calculation with warm-up - Answers must delay the start time by the warm up period then determine the capacity over the post warm up period Capacity flexibility - Answers adjusting capacity to provide a wider range of products and volumes with short lead times Capacity formula - Answers = Total Time/Cycle Time Capacity in product layouts - Answers capacity is represented in units/hour, not minutes/unit and equals the lowest units per hour of a link in the process Capacity management example for transportation costs - Answers slide 19 in capacity management PPT Categories of projects (2) - Answers conventional (low-tech): repetitive projects, tasks, sequences, durations, and resources requirements are known, tested methods are preferred (home construction, well drilling). innovative (high tech): unique projects, non-linear processes, iterations, flexible plans (world's tallest tower, new product development) Change in TAC w/ SS - Answers Average inventory = (Q/2) + SS Class A - Answers Top 15% of items and represent 70 - 80% of total dollar amount Class B - Answers Middle 35% of intermediate items that account for 15% - 25% of total dollar usage Class C - Answers simple inventory controls for stock that collectively represents only 5% of annual dollar volume Combination capacity strategies - Answers trying to shape resources with demand to avoid too much excess capacity, will to have some excess capacity and some customers leave if needed Common Z-values (3) - Answers 90% = 1.28, 95% = 1.645, 99% = 2.33 Competitive priorities (7) - Answers cost (low price on high efficiency/productivity), quality, delivery (fast and reliable), flexibility (wide product/service offering, fast introductions), service (additional value added service), environmentalism, and social responsibility Consideration for increasing capacity (2) - Answers magnitude of demand and incremental cash flow, increasing capacity also creates a new bottleneck Considerations when assigning tasks to stations (3) - Answers task precedence requirements, desired capacity (cycle time), and minimizing number of stations (employees) Control analysis - Answers includes reasons for difference between budget and actual and explanations for improvement Cost factors in inventory management decisions - Answers setup (make)/order(buy) cost, stock out cost, holding cost, and material cost Cost to expedite formula in $/time - Answers (CC - NC)/(NT - CT) CPM conclusion - Answers CPM should be applied for projects and tasks that are repetitive because of estimate reliability from experience CPM definition - Answers used to determine project durations for a given duration of each task, assumes no uncertainty in durations and has no concern about different tasks competing for a limited resource CPM Process (4) - Answers 1. Describe the project - list of activities with their immediate predecessor activities, should be based on the WBS 2. Develop a visual network model 3. Estimate activity durations 4. Determine critical path and slacks Crashing - Answers refers to the expediting of tasks in order to reduce project completion and/or overall project costs Critical activities - Answers activities along the critical path, if any of these are delayed then the whole project will be delayed, management should consider devoting resources from non-critical acitvites to this Critical path - Answers sequence of activities that requires longest total time from start to finish (may have more than one CP in a project) Critical path vs. critical chain - Answers critical path assumes unlimited resources vs. including resource constraints Cross functional integration - Answers financing the capital expenditures, budgeting, and accounting for the related expenses, human resource considerations, information system requirements, marketing and public relations, legal, etc. Cycle time - Answers the time between the completion of two consecutive final steps in a process Delivery quality - Answers process quality (Toyota, McDonalds), defect freee Demand uncertainty example - Answers inventory management ppt slide 28 Dependent demand - Answers demand for an item depends on demand for another item Design quality - Answers product quality (Mercedes, 5 star restaurant), adding features of the product/service Determinants of order winners/qualifiers - Answers determined by relevant and most important competitive priorities Direct costs - Answers reducing duration will increase costs (over time, expedited materials) Economic Order Quantity (EOQ) - Answers how much to order under stable conditions, balances setup/replenishment costs - incentives to make large purchases and holding costs - incentives to make small purchases Effects of roles in a project - Answers have to reallocate project to determine critical path length, may introduce slack and lengthen the time, might have to crash certain project roles to meet target and/or improve probability EOQ formula - Answers = SQRT(2DS/H) *note that H is in $/unit/year and demand is yearly too EOQ limitations (3) - Answers demand is constant and known. replenishment time is known, no shortages are allowed ET formula - Answers = (a + 4m + b+/(6) Event - Answers a point in time that represents the start or completion of one or more activities Examples of constraints that will increase duration (3) - Answers skilled resources (certifications), specialized equipment (cranes), and physical space External factors affecting capacity (2) - Answers government regulations, supplier capabilities Factors enabling global competition - Answers technology (info./comm.), transportation infrastructure, newly industrialized countries, and free trade Fast usage recording - Answers press a button on the shelf whenever an item is taken which is tied to a software system that tracks

Content preview

OPMA 317 - MIDTERM EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026


ABC classification - Answers application of Pareto analysis that divides on-hand inventory into 3
classifications based on annual dollar volume or usage
Activity - Answers a task that consumes time and resources
Additional crashing exercise - Answers pg. 75 of management and scheduling ppt
Additional factors for project success - Answers long-term view would include corporate social
responsibility and environmental performance
Addressing variability in take time in line balancing - Answers add an inventory before an inconsistent
station for a buffer in variability
Adjusting demand with revenue/yield management - Answers adjusting demand patterns using price
structures to flatten demand curves while maintaining service level
Assemble-to-order - Answers half outsourcing to standardize production and half customer specific
production, includes "postponement"
Assembly line balancing steps - Answers 1. Draw a precedence diagram including task times 2.
determine required cycle time (C) to meet demand 3. determine total work time per unit (T) 4.
determine number of work stations needed (N) 5. Assign tasks to stations using trial and error
approach 6. Evaluate efficiency of process 7. redesign the line if not satisfactory
Assembly line balancing steps (3) - Answers draw the precedence diagram, determine the required
cycle time (to complete X in y time we have to finish one x in z minutes), assign tasks to stations
Assembly line example - Answers capacity management ppt, slide 27
Average on hand quantity - Answers average of the saw tooth pattern for inventory, ends up being
(Q/2)
Backflushing - Answers record that product was completed in software which then reduces all
required components for tracking purposes
Base SD % coverage - Answers 1SD 68.2%, 2SD 95.4%, 3SD 99.7%
Benefits for ABC classification (4) - Answers purchasing and supplier development, demand
forecasting, physical inventory control, and inventory counting (check A frequently and C's rarely)
Bottleneck - Answers the slowest part of the a process that constrains capacity
Bottleneck processing time - Answers is equal to the the cycle time for the entire process
Calculating path completion probabilities - Answers to determine if a path can be completed by a
certain date consult the z score
Calculating project duration for a confidence level - Answers solve for D in the z-score formula to
determine number of days to produce a certain duration with a certain confidence
Capacity - Answers the maximum production output possible in a time period
Capacity calculation with warm-up - Answers must delay the start time by the warm up period then
determine the capacity over the post warm up period
Capacity flexibility - Answers adjusting capacity to provide a wider range of products and volumes
with short lead times
Capacity formula - Answers = Total Time/Cycle Time
Capacity in product layouts - Answers capacity is represented in units/hour, not minutes/unit and
equals the lowest units per hour of a link in the process
Capacity management example for transportation costs - Answers slide 19 in capacity management
PPT
Categories of projects (2) - Answers conventional (low-tech): repetitive projects, tasks, sequences,
durations, and resources requirements are known, tested methods are preferred (home construction,
well drilling). innovative (high tech): unique projects, non-linear processes, iterations, flexible plans
(world's tallest tower, new product development)
Change in TAC w/ SS - Answers Average inventory = (Q/2) + SS
Class A - Answers Top 15% of items and represent 70 - 80% of total dollar amount
Class B - Answers Middle 35% of intermediate items that account for 15% - 25% of total dollar usage
Class C - Answers simple inventory controls for stock that collectively represents only 5% of annual
dollar volume
Combination capacity strategies - Answers trying to shape resources with demand to avoid too much
excess capacity, will to have some excess capacity and some customers leave if needed
Common Z-values (3) - Answers 90% = 1.28, 95% = 1.645, 99% = 2.33

, Competitive priorities (7) - Answers cost (low price on high efficiency/productivity), quality, delivery
(fast and reliable), flexibility (wide product/service offering, fast introductions), service (additional
value added service), environmentalism, and social responsibility
Consideration for increasing capacity (2) - Answers magnitude of demand and incremental cash flow,
increasing capacity also creates a new bottleneck
Considerations when assigning tasks to stations (3) - Answers task precedence requirements, desired
capacity (cycle time), and minimizing number of stations (employees)
Control analysis - Answers includes reasons for difference between budget and actual and
explanations for improvement
Cost factors in inventory management decisions - Answers setup (make)/order(buy) cost, stock out
cost, holding cost, and material cost
Cost to expedite formula in $/time - Answers (CC - NC)/(NT - CT)
CPM conclusion - Answers CPM should be applied for projects and tasks that are repetitive because
of estimate reliability from experience
CPM definition - Answers used to determine project durations for a given duration of each task,
assumes no uncertainty in durations and has no concern about different tasks competing for a limited
resource
CPM Process (4) - Answers 1. Describe the project - list of activities with their immediate predecessor
activities, should be based on the WBS
2. Develop a visual network model
3. Estimate activity durations
4. Determine critical path and slacks
Crashing - Answers refers to the expediting of tasks in order to reduce project completion and/or
overall project costs
Critical activities - Answers activities along the critical path, if any of these are delayed then the whole
project will be delayed, management should consider devoting resources from non-critical acitvites to
this
Critical path - Answers sequence of activities that requires longest total time from start to finish (may
have more than one CP in a project)
Critical path vs. critical chain - Answers critical path assumes unlimited resources vs. including
resource constraints
Cross functional integration - Answers financing the capital expenditures, budgeting, and accounting
for the related expenses, human resource considerations, information system requirements,
marketing and public relations, legal, etc.
Cycle time - Answers the time between the completion of two consecutive final steps in a process
Delivery quality - Answers process quality (Toyota, McDonalds), defect freee
Demand uncertainty example - Answers inventory management ppt slide 28
Dependent demand - Answers demand for an item depends on demand for another item
Design quality - Answers product quality (Mercedes, 5 star restaurant), adding features of the
product/service
Determinants of order winners/qualifiers - Answers determined by relevant and most important
competitive priorities
Direct costs - Answers reducing duration will increase costs (over time, expedited materials)
Economic Order Quantity (EOQ) - Answers how much to order under stable conditions, balances
setup/replenishment costs - incentives to make large purchases and holding costs - incentives to
make small purchases
Effects of roles in a project - Answers have to reallocate project to determine critical path length, may
introduce slack and lengthen the time, might have to crash certain project roles to meet target and/or
improve probability
EOQ formula - Answers = SQRT(2DS/H) *note that H is in $/unit/year and demand is yearly too
EOQ limitations (3) - Answers demand is constant and known. replenishment time is known, no
shortages are allowed
ET formula - Answers = (a + 4m + b+/(6)
Event - Answers a point in time that represents the start or completion of one or more activities
Examples of constraints that will increase duration (3) - Answers skilled resources (certifications),
specialized equipment (cranes), and physical space
External factors affecting capacity (2) - Answers government regulations, supplier capabilities

Document information

Uploaded on
July 31, 2026
Number of pages
7
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$11.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.4
(74)
Sold
484
Followers
16
Items
32665
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions