Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 78 pages
Exam (elaborations)

PMI CAPM EXAM– QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS PLUS RATIONALES | GUARANTEED PASS | LATEST EXAM UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST| DOWNLOAD INSTANT PDF

Document preview thumbnail
Preview 4 out of 78 pages

PMI CAPM EXAM– QUESTIONS AND ANSWERS | VERIFIED AND WELL DETAILED ANSWERS PLUS RATIONALES | GUARANTEED PASS | LATEST EXAM UPDATE | EXAM PREP | STUDY GUIDE | PRACTICE TEST| DOWNLOAD INSTANT PDF

Content preview

PMI CAPM EXAM– QUESTIONS AND ANSWERS | VERIFIED
AND WELL DETAILED ANSWERS PLUS RATIONALES |
GUARANTEED PASS | LATEST EXAM UPDATE | EXAM PREP |
STUDY GUIDE | PRACTICE TEST| DOWNLOAD INSTANT PDF
1. A newly appointed project manager is reviewing the project charter to understand the
high-level objectives, project boundaries, and key stakeholder requirements. Which of the
following best describes the primary purpose of the project charter?

A. To provide a detailed breakdown of individual work packages and schedule network
diagrams

B. To formally authorize the existence of the project and provide the project manager with the
authority to apply organizational resources

C. To outline the specific technical specifications and quality metrics for each deliverable

D. To establish the definitive final budget and contractor compensation rates

ANSWER: B. To formally authorize the existence of the project and provide the project
manager with the authority to apply organizational resources

The project charter formally authorizes the project's existence and empowers the project
manager. Detailed work packages and network diagrams belong to the project management
plan and schedule baseline, not the high-level charter.

2. During a project team meeting, a stakeholder requests an additional feature that falls
outside the current project scope baseline. What is the first action the project manager
should take?

A. Immediately update the project schedule to accommodate the new feature request.

B. Reject the request outright to protect the project scope from creeping.

C. Direct the stakeholder to submit a formal change request through the integrated change
control process.

D. Implement the feature if team capacity allows without consulting documentation.

ANSWER: C. Direct the stakeholder to submit a formal change request through the
integrated change control process.

Any scope modification must follow the formal change control process to evaluate impacts on
schedule, cost, and risk before approval or rejection by the change control board.

,3. A project team is working in an agile environment and needs to prioritize backlog items
for the upcoming sprint based on business value, risk, and dependencies. Who holds the
ultimate authority for prioritizing the product backlog?

A. Project Manager

B. Scrum Master

C. Product Owner

D. Lead Developer

ANSWER: C. Product Owner

In agile methodologies, the Product Owner is responsible for managing and prioritizing the
product backlog to maximize the value of the product resulting from the work of the
development team.

4. A project manager is calculating the schedule variance (SV) for a construction project.
The earned value (EV) is $450,000 and the planned value (PV) is $500,000. What does this
indicate about the project schedule?

A. The project is ahead of schedule.

B. The project is behind schedule.

C. The project is perfectly on schedule.

D. The project is under budget.

ANSWER: B. The project is behind schedule.

Schedule variance is calculated as SV = EV - PV. Here, $450,000 - $500,000 = -$50,000. A
negative variance indicates that the project is behind schedule because less work has been
completed than planned.

5. While managing a software development project, the project manager identifies a risk
regarding potential server downtime during deployment. The team decides to purchase
insurance to cover potential losses. Which risk response strategy is being implemented?

A. Avoid

B. Mitigate

C. Transfer

,D. Accept

ANSWER: C. Transfer

Purchasing insurance or warranties shifts the financial impact of a risk to a third party,
which defines the risk transfer strategy.

6. A project manager is conducting a stakeholder analysis and maps various stakeholders
onto a power/interest grid. Which stakeholder group requires the highest level of active
engagement and regular management attention?

A. Low power, low interest

B. High power, low interest

C. Low power, high interest

D. High power, high interest

ANSWER: D. High power, high interest

Stakeholders with high power and high interest are key players who can significantly impact
project success and therefore require close management and active engagement.

7. A project team is estimating the duration of a complex engineering task using three-
point estimating (PERT). The most likely duration is 15 days, the optimistic duration is 9
days, and the pessimistic duration is 27 days. What is the expected activity duration?

A. 15 days

B. 16 days

C. 18 days

D. 21 days

ANSWER: B. 16 days

The PERT expected duration formula is (Optimistic + (4 * Most Likely) + Pessimistic) / 6.
Substituting the values: (9 + (4 * 15) + 27) / 6 = (9 + 60 + 27) / 6 = = 16 days.

8. An agile team has just completed a sprint and is holding a meeting to inspect processes,
identify opportunities for improvement, and create an action plan for the next iteration.
What is this meeting called?

A. Sprint Planning Meeting

, B. Daily Standup

C. Sprint Review

D. Sprint Retrospective

ANSWER: D. Sprint Retrospective

The sprint retrospective is specifically dedicated to team self-inspection and process
improvement. The sprint review focuses on inspecting the increment and adapting the product
backlog.

9. A project manager discovers that a key regulatory requirement was omitted from the
project scope during initiation. The requirement must now be integrated. Which document
should be updated first to reflect this change formally?

A. Project Management Plan

B. Project Charter

C. Issue Log

D. Work Breakdown Structure

ANSWER: A. Project Management Plan

Once baseline plans are established, approved changes to scope, schedule, or cost are
integrated and controlled through updates to the project management plan and its subsidiary
baselines.

10. A project team is experiencing conflicts regarding task assignments and technical
approaches, leading to friction and decreased productivity. According to Tuckman's ladder
of team development, what stage is the team currently experiencing?

A. Forming

B. Storming

C. Norming

D. Performing

ANSWER: B. Storming

Document information

Uploaded on
July 28, 2026
Number of pages
78
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$25.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Sold
3
Followers
1
Items
787
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions